Round Tracker v4 PRO – User Guide


The top row of the calendar shows the total amount of work that is due on this particular day according to the present forecast.


The bottom row of figures shows a subtotal of work due when a filter is applied. (eg. Priority A)


Re-scheduling Work


From time to time due to bad weather or unforeseen events it is inevitable that work falls out of schedule. If you use intervals which are a multiple of 7 and also enter a preferred day then it is easy to identify work which has fallen out of schedule by referring to the calendar.


The jobs shown in red on the calendar are those which fall on a day different to that stipulated in the Preferred Day column.


Another, perhaps easier way of quickly identifying work which has fallen behind is to click the Late icon.


This performs an automatic filter for all work which is overdue.


The Days Late column shows the amount of days that the work is overdue.


21


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56