FEATURE INDUSTRIAL BUILDINGS


RAIL WORKSHOP CONSTRUCTED in less than four months


Urgently needing extra space, SB Rail had a workshop designed, built and ready to move into within four months. Less complex foundations allowed site work to proceed rapidly


N


eeding extra space urgently, rail network infrastructure maintenance


contractor SB Rail turned to instant building specialist Smart Space who designed, built and handed over a new workshop in less than four months. Being based on a light yet strong construction system, less complex foundations were required, allowing site work to proceed rapidly. The new workshop is comparable to a conventional new-build though construction costs were less than half. SB (Swietelsky Babcock) Rail is a joint


venture specialising in maintenance of the trackbed and operates specialised vehicles for rail, ballast and power infrastructure maintenance. Taking over an old service depot and having vehicles larger than could be housed, a new workshop was essential to permit efficient servicing.


LESS COMPLEX GROUND WORKS The Smart Space permanent building uses a lightweight cold-rolled galvanised steel framework in place of hot rolled steel girders and joists. These structures are strong but much lighter than conventional buildings. In addition to reduced construction cost they impose a lower ground loading than standard buildings and so usually require less complex ground works, giving rise to


further significant time and cost savings. The Smart Space system can be clad in any standard sheeting material. This gives the end user a choice of colour, profile, window and door style. Cladding may be specified in corporate colours and matched to that of existing buildings. Fully insulated cladding systems are generally used so that buildings conform fully to Part L of the current Building Regulations. Electrical and mechanical services can be installed


Based on a light yet strong construction system, less complex foundations were required, allowing site work to proceed rapidly


to meet the user’s individual needs. Workshops are just one of many applications. Smart Space permanent buildings are often used as garages, factories, warehouses, changing and mess rooms and even sports halls. “The system is flexible enough to adapt


to many applications,” comments managing director Antony Hunt. “We have even upgraded the system to


provide eco-classrooms for a school, beefing up the insulation levels and using underfloor heating powered by an air source heat pump to meet low CO2 emission targets. A similar approach could easily be applied to provide offices or retail space.” “From placing the order to the


completed structure being handed over for fit-out took less than four months,” says SB Rail plant manager Neil Smith. “The contract was carried out in an


efficient professional manor from the surveying staff right through to the fitters and commissioning engineers. Having been in the building over a year now we have no regrets in going for the Smart Space permanent building and have been happy to allow others to see what they have done for us.”


Fully insulated cladding systems are generally used so that buildings conform fully to Part L of the current Building Regulations


10 DECEMBER 2014/JANUARY 2015 | FACTORY EQUIPMENT


Smart Space T: 01827 330000 www.smart-space.co.uk Enter 302


/ FACTORYEQUIPMENT


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56