This page contains a Flash digital edition of a book.
WORKSHOPS, DEPOTS AND MANUFACTURING XXXX


will be extended by Network Rail under their eight-car works for Southern, by March 2014.


Train storage, maintenance and signalling


Sidings and depot facilities have also had to be altered to cater for the longer trains.


A major part of the project is Silwood Triangle, where 10 trains will be stabled. It was chosen because London Overground already owned the land, and because it is close to the New Cross Gate depot. The site, in north Lewisham, needed full planning consent – but Edwards told us that achieving this was better than plumping for a sub-optimal site just to get around the difficulties associated with the planning process.


Work at the site began in April 2013, and should be finished by April 2014. It includes revisions to track alignment, new track and walkways, infrastructure for the signalling, and new staff welfare buildings, fencing, car parks and access roads.


modifications to other equipment within the depot so the longer trains can be maintained and to allow the trains to be converted from four to five carriages on site. These works will be complete by October 2014.


The headshunt at New Cross Gate station is also being extended.


Separately, the Willesden Junction train


maintenance depot is being extended towards the station, and London Overground is also deciding on a new stabling/cleaning facility to accommodate 12 five-car trains in north London.


These works require extensive signalling


changes at the depots and stabling facilities, and linewide alterations including the moving of starting signals and stop markers, the relocation of axle counters,


and


modifications to the Train Protection Warning System (TPWS) and Automatic Warning System (AWS). The signal changes will have a “slight impact” on train timetabling, meaning there will be consequent changes to the Train Describer (TD),


Customer


Information Screens (CIS) and Automatic Route Facility (ARF).


New carriages


The first longer train enters service on the East London Line in late 2014. In total, 29 trains are being extended on the ELL, one a week for just over half a year.


Edwards said making use of the Silwood site was a “good win” for London Overground, adding: “There was a discussion about utilising Network Rail sidings down towards the Norwood Junction or West Croydon, but we’ve gone for sidings near our central core – it’s a turnout off our infrastructure that London Overground owns and maintains. It’s a piece of scruffy scrub land which was light industry and scrapyards,


very


much brownfield, which we’ve redeveloped in a big way.”


Cleshar is the contractor for the majority of the works in the Silwood Triangle.


There are also ongoing depot reconfiguration and station works at New Cross Gate, being delivered by Spencer: extension of the train maintenance shed northwards; extension of the wheel lathe/heavy cleaning shed northwards; changes to the interior layout of the sheds to accommodate the longer trains; alterations to the bays used to store and maintain the trains to stable 13 five-carriage trains instead of 21 four-carriage trains; and


Edwards said: “The insertion of the fifth car will happen at New Cross Gate, unlike when we went from three-car to four-car a few years ago, when it was done at Derby. To reduce outage time, we’re going to take the unit out of operational service for a week, insert the fifth car, fully commission, fully test, and send it back out into operation.”


Of course, all the fixed infrastructure works have to be ready for that first extended train.


London Overground will also need new drivers, because although it’s an extension rather than expansion, Edwards said changing stabling arrangements means changing driver rosters and a need for more drivers.


The main marketing campaign promoting the five-car extension to passengers will begin in summer 2014.


Commenting on the tight timescales of this project, Edwards told us: “When compared to a traditional DfT or Network Rail programme of work, the pace of delivery here is significantly faster. We’ll bring in the first fifth car at the end of 2014, when we didn’t gain board approval to do the work until February


The traction maintenance depot at Willesden Junction


2013. I often say it’s a three-year programme of work delivered in 18 months.”


That means taking risk-based decisions along the way, such as buying the switches and crossings seven months before detailed design was actually completed. “They become a fixed point,” Edwards said, “so we said ‘right, we’ve ordered the S&C, everything has to fit around them’. That’s how London Overground has developed, making risk-based management decisions and design decisions along the journey based on the information known at the time. We’ve been successful in doing that.”


The future


Edwards acknowledged that over a 20 or 30-year timeframe, the five-car extension alone will not be nearly enough to offer the capacity required, although Crossrail will help from 2018.


But the Class 378s can’t be configured to run in six-car formation, so Edwards said the next opportunity for serious capacity improvement after this extension would be at fleet renewal time in the mid-2020s.


Until then, LOROL could run additional train services – going from 16tph on the East London Line core to 18tph, for example. Going beyond that would require ATO (automatic train operation), Edwards suggested, copying the example of the Thameslink core, Crossrail, and London Underground.


He told RTM: “If we stretched and sweated the fleet, we believe we could be running an 18tph service between Shoreditch and New Cross Gate. But the reality is, that’s not where demand is – the demand is south. The demand is for bringing passengers up from the Crystal Palace, West Croydon areas into the central core. So therefore [we are in a] tricky position; that’s where the demand is, that’s where the business case is – unfortunately that’s not where the paths are…so the next discussion to be had with the industry is ‘can we sweat two additional paths south of New Cross Gate’.”


Huw Edwards


www.tfl.gov.uk/londonoverground FOR MORE INFORMATION


rail technology magazine Dec/Jan 14 | 77


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112