Fish Passes & River Structures
The next part of the project included the replacement of the existing water control structure.
The original water control was a sluice gate structure (as seen below), which had to be opened manually in the event of a flood. This was a potentially dangerous and labour intensive task.
Weir near completion
Over pumping to maintain dry working areas
www.managingwater.co.uk
The existing sluice was replaced by a new fixed crest weir which reduces the danger and the reliance on manual operation. The construction required the installation of a sheet piled coffer dam with over pumping during the construction phase to ensure safety and access.
For more information contact Land & Water The weir in flow conditions
LAND & WATER REACHING HIRE STANDARDS
OPERATED OR SELF-DRIVE HIRE
Low & High Flow Auxiliary Circuits - Standard
All Plant Sourced From EU Dealers to Full EU Standards
Hose Burst Check Valves - Standard
Approved Lifting Point & Safe Working Load - Standard
Bucket Ram Guard - Standard
Operator Handbooks Machine
Certification - Standard
Free Site Visits, Advice & Solutions from a Supplier of Long Reach Excavators for Over 25 Years
Biodegradable Hydraulic Oil - Standard
Cab Guards - Standard
Latest E.U Low Emission Engine - Standard
LGP Tracks - Standard
Also Available: Pontoons, Weed Boats, Tugs, Amphibious Excavators, Barges etc. National Service. Complete range of attachments.
NATIONAL HIRE DESK 01483 203070 25
www.fadsdirectory.com
The UK’s
Largest Fleet of Long Reach Excavators
Long Reach Excavators
from 3 Tonnes to 115 Tonnes
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36