This page contains a Flash digital edition of a book.
Feature 1 | GREEN SHIP TECHNOLOGY Triality tanker design interests owner


DNV’s new tanker design presented to the public in early December in London is a “refreshing” concept said Maersk. Te design incorporates a new hull geometry with existing technology that could reduce CO2


emissions substantially. I


n designing the new Triality tanker the DNV team set out to determine what would be the over-riding


needs for the future and they concluded, very quickly, that the environmental footprint of the ship was of paramount importance. Solutions for reducing emissions


needed to be simple, there was to be “no complexity to the ship,” explained Torrill Grimstad Osberg, Triality project manager. “We were working with a knife at our throats,” she laughed describing the short time scale that was afforded the team to come up with a new concept vessel. In fact the DNV team started work in mid-August and had completed their work in just three months. With these parameters and the short


time scale in mind it was a relatively simple step to decide that the fuel the new ship should use would have to be liquefied natural gas (LNG). It was the only fuel available that would reduce all the key emissions, substantially, including CO2


by


34%, SOx and particulate matter by 94% and NOx by 82% for the Triality vessel as a whole. That meant more time could be


afforded to the design of the hull which was, said Ms Grimstad Osberg, the most challenging element of the vessel design. Te rest of the ship has been fitted with existing technology.” Maersk’s manager of the innovations


department Gunnyar Bjornsson, who is a naval architect and master mariner and specialises in the use of LNG as a fuel, was impressed by the hull design and the ballast free elements of the concept vessel. “It’s a completely different geometry, on an ordinary tanker the cross section is rectangular, with the Triality it is a V-shape, but with a 10m or so flat bottom”. However, with the ship operating at a


draſt of around 8m aſt and 6m at the bow when operating empty there could be


42


The 300,000dwt tanker has a 70m beam giving it extra stability in its, ballast free, empty operational mode.


issues with stability, agreed Mr Bjornsson, who had also seen DNV’s presentation on the Triality vessel. “I couldn’t tell about stability without model tests and further calculations, but there would definitely be an issue there, particularly when manoeuvring and in a beam sea.” Tough he did not consider these design difficulties insurmountable. In fact a mitigating factor for the vessel


would be its 70m beam, which is 10m wider than the standard VLCC. Te vessel has also been made longer at 361m and has a loaded draſt of 21.6m. Loading of


Two large deck houses contain the cargo tanks, each of 6750m3 range of 25,000nm.


giving an operational


the vessel, which has its tanks arranged five across, would have to be completed by filling all the centre tanks simultaneously to prevent bending moments. However, the shallow draſt of the vessel


when operating empty did create another problem with the propeller. It meant that the team opted for two MAN ME-GI engines with direct drives for two 7m overlapping propellers rather than the standard single 9-10m propeller which would have been too large for the shallow draſt vessel. Te two propellers overlap by 1m and


give “extra efficiency”, said Ms Grimstad Osberg and the cost of two smaller MAN engines compared to a single larger engine “was not great”, she added. A tougher nut to crack, however, has been the dilemma over CO2


emissions


and in this case DNV opted for LNG as the best possible existing technology. Although Ms Grimstad Osberg conceded that LNG is not the only answer to the maritime sector’s emissions conundrum she said that the fuel would reduce CO2 by around 34% while particulates and SOx


The Naval Architect January 2011


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72