Offsite steel frame completes Staffordshire student village


A new Student Village at the University of Staffordshire has been completed aſter its superstructure was delivered using an offsite light gauge steel frame system.


The £100m development in Stoke-on-Trent was delivered under a Design, Build, Finance, Operate model by a consortium comprising Willmott Dixon, HOCHTIEF PPP Solutions UK and Ireland, Plenary and Pinnacle Group, working with the university. The project is described by Willmott Dixon as a 715-bed development, while the university says the wider Student Village provides 1,000 new and refurbished bedrooms. The completed village therefore combines newly constructed accommodation with refurbished bedrooms.


The MMC strategy centred on an integrated light gauge steel frame solution manufactured off site before being assembled across six residential buildings. The superstructure was completed in 32 weeks, with manufacturing tolerances


maintained to 5mm across the development. The village opened in September for the new academic year and includes a pedestrian bridge connecting the accommodation to the university’s main Leek Road campus.


Light gauge steel framing is an established form of panelised offsite construction, allowing structural components to be manufactured under controlled conditions before arriving on site for assembly. The Staffordshire project demonstrates how MMC can be incorporated into a large development without requiring the entire building to be manufactured as volumetric modules. Instead, the structural system is industrialised while other elements are completed through more familiar construction processes.


That distinction is increasingly relevant as clients look for ways to adopt MMC selectively. Panelised approaches can offer the benefits of factory production while retaining flexibility in building layouts and site assembly.


The DBFO model also gives the delivery team a long-term interest in the completed accommodation, with performance and operational requirements considered alongside the initial construction programme. The completed Student Village adds another substantial UK case study to the evidence around offsite steel construction in education and residential development.


Skanska uses offsite MEP modules on constrained Mayfair project


Skanska has used two offsite-manufactured multi-service MEP modules to overcome access and programme constraints at the South Molton development in Mayfair, London.


The development for Grosvenor and Mitsui Fudosan UK comprises two buildings in one of London’s most constrained construction environments. Installing mechanical, electrical and public-health services within confined riser spaces presented a significant sequencing challenge.


Skanska worked with its specialist supply chain to manufacture bespoke steel-framed modules away from site. Services from multiple partners were assembled within a controlled production environment before the completed modules were transported to Mayfair and liſted into position. According to Skanska, an installation process that would traditionally have taken around nine weeks per riser was reduced to two planned weekend liſting operations. The modules were craned into the buildings and connected on site.


The example demonstrates the value of applying MMC at component level rather than treating offsite construction as an all-or-nothing decision. Multi-service modules can bring together several trades and systems before delivery, reducing the amount of sequential work required in restricted areas. The approach also changes where work takes place. Rather than assembling individual services inside a confined riser, the different systems can be coordinated and installed within a controlled manufacturing environment before the module reaches the building.


Skanska said the factory environment allowed the work to be inspected and controlled throughout manufacture, providing an additional quality-control benefit.


For urban projects, logistics remains an important part of the calculation. A completed module still has to reach the site, be liſted into position and connect correctly with surrounding construction. Early coordination between designers, manufacturers, logistics teams and site contractors is therefore essential.


South Molton provides a useful example of how DfMA can be applied to a specific construction constraint without requiring an entire project to adopt one MMC system. The approach also demonstrates how offsite manufacture can be used to remove particularly difficult activities from a live construction site, rather than attempting to industrialise every element of a project.


6 Autumn 2026 M41


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44