The last mile of MMC


For all the attention given to factory production, one of the most important parts of an offsite construction project happens aſter the manufacturing is finished. A module can be designed digitally, manufactured to tight tolerances and completed with services and finishes before it leaves the factory. None of that matters if it cannot reach the site safely, on time and in the condition in which it leſt. MMC Magazine editor explores how the final journey from factory to building site is more than a transport exercise. It is part of the construction process, and for some MMC projects it can be one of the most difficult parts to plan.


T


he UK’s Government research into volumetric modular construction describes transportation as a critical part of the lifecycle. Its review identifies risks including damage in transit, long travel distances, unsuitable road conditions, inadequate vehicles and difficulties securing modules safely. Those risks are amplified when a component is large, heavy, finished or dimensionally fixed. A traditional construction material can oſten be cut, adjusted or reordered around site conditions. That makes logistics an early design issue.


A project team needs to know the likely route, vehicle requirements, delivery sequence, liſting arrangements and site access before manufacturing begins. Bridge restrictions, road geometry, overhead obstructions, weight limits and turning areas can all affect whether a proposed solution is practical.


For constrained sites, the question can become even more fundamental: can the finished component physically get there?


Urban constraints


Dense urban locations present a particular challenge. Construction sites may have limited storage, narrow access roads, restricted working hours and little room for cranes or delivery vehicles.


Traditional construction can spread deliveries 20 Autumn 2026 M41


across many trades and materials. MMC can reduce the number of separate site operations, but it can also concentrate the consequences of a missed delivery. If a critical module arrives late, the installation sequence may have to stop. This creates a tension at the heart of offsite delivery. Manufacturing rewards repeatability and efficient production. Sites oſten involve uncertainty, changing conditions and limited space. The solution is not to make factories less efficient. It is to connect manufacturing schedules much more closely with site logistics.


Just in time, but genuinely


“Just in time” is oſten used in discussions about MMC, but it is easy to misunderstand. Delivering components just before installation only works when the whole chain is coordinated.


A module that arrives too early may have to be stored, creating additional handling and exposure. One that arrives too late can disrupt cranes, installers and other trades. A delivery that reaches the site at the right time but cannot be unloaded because another operation is occupying the access route is no more useful.


The Government’s research recommends early assessment of transport requirements, including the size and weight of modules, distance, route and protection from environmental conditions. It also stresses the importance of clear


responsibility when damage is discovered.


That is a useful reminder that logistics is not simply about booking a lorry. It requires planning, communication and defined ownership.


Damage before the building site


The risks also change when modules are highly finished.


A structural frame can be relatively tolerant of handling damage that is visible and easily repaired. A completed module containing plumbing, electrical systems, finishes, doors, windows or other installed components can carry much more value and complexity.


Damage to a finished unit may not always be immediately obvious. The Government’s research highlights concerns around damage during transport and liſting, including the possibility that defects affecting performance may not be identified before installation. That creates a quality-control requirement extending beyond the factory gate. Inspection needs to happen when components arrive, and teams need to know what constitutes acceptable condition, who records defects and who is responsible for remedial work. Without that process, a dispute about whether damage occurred during manufacturing, transport, liſting or installation can quickly become a programme problem.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44