Flues? it’s not all hot air for data centre construction


F


It’s well known that a large number of data centres are needed to meet demand by the middle of the decade, yet construction is often plagued by delays and complications. Dean Moffatt, Schiedel’s technical sector expert, explains how an often overlooked piece of structural equipment has the potential to eliminate the risk when contractors take on new projects


rom 2015 to 2021, data centre workloads increased by 260%. This trend will continue, if not increase further, driving demand for new data centres in key markets across the world.


But construction in this sector faces a huge challenge. According to Savills, planned data centre development across Europe needs to more than double by 2025 to keep pace with new users, restating the need for effective project management with minimal delays. Despite this, a key part of the build and commissioning process continues to be overlooked – the flue.


Simple but significant


The seemingly simple role of a flue means its significance is often overlooked. However, they are key to designing out problems during construction, not to mention essential for owners and operators when uptime is threatened. Tier IV classification, for instance, can only be achieved when a facility can prove a sufficient level of fault tolerance. Flues are central to demonstrating that concept, allowing back-up generators to run smoothly in the event of a mains outage. But chimneys are also mission critical for the construction of data centres, and factoring them in at the earliest point is important for minimising delays and anticipating problems before they affect the project’s timeline. Timing is key. If the incorrect product is specified or installed at the wrong point, it will likely impact the installation of other key building services. This pushes back commissioning and risks late handover to the owner or operator, damaging the reputation of businesses who often win work in this sector based on reputation alone.


Following the critical path


Being inexpensive in the context of a wider build, flues are often left until the last minute in new data centre projects. This is a mistake. At Schiedel, we advocate a ‘flue first’ approach, incorporating it into the building’s critical path. Why? Because engaging a flue specialist at the earliest point means problems are less likely to occur ahead of handover. Treating flue installation as an afterthought often leads to on-site contractor clashes and remedial action to fit a chimney around other building services. It’s not uncommon, for example, to find HVAC equipment or power


cabling running across the route where a chimney is meant to be installed. Flue first avoids this stumbling block.


The capabilities and specification of the flue itself are also crucial to the success of any new data centre project. Schiedel’s approach allows for joint design between the OEM specialist and contractor, ensuring sufficient testing is completed ahead of installation. This issue is growing in importance as data centres move closer to urban areas to lower latency. Research shows outages are growing in length, meaning generators are running for longer near residential areas. Chimneys that are not up to the job will spread harmful fumes and fail to manage the noise created by back-up power. Clearly, this is an untenable situation for any business taking ownership of a new data centre. Getting the flue right the first time ultimately avoids complications once a data centre is live, providing reassurance to owners and operators. If power does go out, there is a good level of redundancy supported by the flue, in turn avoiding expensive remedial work later down the line. By following the critical path and appointing specialists like Schiedel, recurring yet easily avoidable issues can be designed out of data centre projects for good. This will allow contractors to be paid on time, free up time for other projects necessary to meet development targets, and provide owners and operators with a more resilient facility.


Getting the flue right


the first time ultimately avoids complications once a data centre is live, providing reassurance to owners and operators. If power does go out, there is a good level of


redundancy supported by the flue, in turn avoiding expensive remedial work later down the line.


10 BUILDING SERVICES & ENVIRONMENTAL ENGINEER SEPTEMBER 2023


Read the latest at: www.bsee.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46