search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
INSIGHT | FINANCE, RISK, PROCUREMENT


HOPES, PLANS AND CHALLENGES ONGOING


Time and cost are the focus on recent reviews and discussions on planning and executing HS2 and Sizewell C projects. Report by Patrick Reynolds.


HS2’s Northolt Tunnel.


Recent report from the government and the National Audit Office (NAO) have looked at two major infrastructure projects with underground elements of different degree: High Speed Two rail project (HS2) and Sizewell C nuclear power plant, respectively. What the large construction schemes have in common is the concern among many over cost and completion timelines. HS2 may be far more advanced but is very late and well


over budget already, and in the midst of a consequential reset; Sizewell C is in relatively early stages but draws upon experience of a prior major nuclear power plant project in the UK. As such, HS2 flagged its reset needs and agenda last


year and work has been underway on the task since then, and was recently updated by government. The NAO have looked over the project and reset, too, and at the end of June shared its views. Both reviews on HS2 project are discussed below. NAO also conveyed its cautionary advice on Sizewell C’s “novel finance structure” in the previous month, May, and the key points are also discussed below.


HS2 The NAO comments, in its report on HS2 out at the end of June, that the cost of Phase 1 of the large-scale rail project


30 | July 2026


“increased significantly” since 2020, doubling in effect to somewhere in the range of £87.7 billion to £102.7 billion. Those are the same figures released the month before,


by the Department for Transport (DfT), when Transport Secretary Heidi Alexander briefed Parliament on the latest cost estimates. She added that one third of the total budget increase in the project is due to inflation, while the balance - the majority - is due to works missed from the original project scope and delivery inefficiencies. Given the range of the cost estimates, decimal accuracy


might not be the key factor to follow to get a sense of the jump in cost and to the level where it is expected to sit. Broadly, the range can be taken to be from near £90 billion to slightly more than £100 billion. Bottom line, there is little change to be left from £100 billion, relatively. And, in return for that outlay the project is anticipated


now to open about 13 years late - or at least later than that planned for erroneously in weak evaluations at the outset, when there was a rush to get going. It is now known that the best of preparations and oversight were not performed, according to what the official assessments have found. Yet there have been excellent engineering achievements, above and below ground, and while most tunnelling has been completed the final main works are


All Images courtesy of HS2 Ltd


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45