search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
BTS | LA METRO


part of the route passes through siltstone, which would be difficult to process with a slurry machine. The panel also said that if a one-pass liner system was used it should not preclude adding a second liner in future (if there was leakage of gas or water), for it to be acceptable. Additional investigation included reducing boring


Top and right and far right: Complete Red Line stations and artwork.


spacing to less than 100m, using continuous core borings, and the panel also recommended doing a large exploratory shaft to better understand the unique ground conditions (tar sands, gas, fossils). The 23m-deep box shaft (built with soldier piles and shotcrete) was located at Fairfax station, in Section 1, and considered very successful in removing the mystique as during the proposal stage bidders could visit. Palaeontology had to be considered in the contract


Above and below: Convex joint seismic design for Gold Line.


documents. The GBR has a ‘paleo layer’ within which excavation could only proceed in thin (6-inch (150mm)) lifts to avoid disturbing fossils. While that would slow things down, it was included in bids as it was an environmental mitigation. A palaeontologist was on site during investigations. The final geological profile for the Purple Line Extension included: old and young alluvium, liquefiable San Pedro Formation, and some siltstone on the east side. In the Wilshire/Fairfax area, the profile shows the top of the asphalt-impregnated soil. The TBMs were similar to those on the Gold Line. There


were two new TBMs for each section and the double gaskets were used, with cross gaskets, for lining. On Section 1 of the extension there was a need for soil


conditioning of the tar-infused soil. Additional tests were performed, including in Italy. The TBMs broke through into and were pulled through


stations. One change from the earlier Purple Line work was that columns were removed from the stations, resulting in a slightly narrower station with an arched


roof. The single-pass linings were the same size as on the Gold Line. Although heavy rail requires about a foot less diameter than light rail, the final size came out about the same as the tunnel was sized so that a remedial secondary liner could be added at a future date. For the Purple Line Extension, the cross gasket is on


the circumferential joint. Based on these experiences the cross gasket is now codified in LA Metro criteria to be on the longitudinal joint. Tunnelling went very well. Average settlement was less than allowable, including in sensitive areas such as Beverly Hills. Bentonite shield-gap grouting was judged to have contributed to reduced settlement, although not all contractors chose to use shield grouting. Tunnelling in gassy conditions also went well. There


were, however, a few exceedances of OSHA allowable gas limits in one reach of tunnel, requiring brief evacuation until Cal/OSHA gave the all-clear to return. In a portion of Reach 3 of the Section 1 tunnel, soil


vapour extraction was used to reduce hydrogen sulphide and methane concentrations. This had been planned for many years as a potential mitigation measure. The concept is that air is injected through some wells and extracted through others, neutralising hydrogen sulphide gas in the ground. The tunnelling works were then able to pass through the area without issues. Air in local building basements was monitored and any gas oxidised. Amanda handed back to Matthew, who continued the briefing to its conclusion.


PURPLE LINE: CONSTRUCTION SUCCESSES AND DIFFICULT INTERFACES Station construction took the same basic approach used for 35 years, although with a few points of note. During Covid shutdowns, complete street closures were possible in the Golden Triangle in Beverly Hills, which


Right and far right: Double gasket system. 16 | June 2026


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53