Grid Transmission Procurement – Indicative Timing Interface with Suffolk CC and LPAs


RFQ Issue


April ‘13


Initial Bid 4months


Initial design proposals


Evaluation (4 months)


RFQ


Receipt Sept ‘13


Shortlist


Recommendation Jan ‘14


Design optimisation Complete May‘14


Optimised Bid


4 months


Optimised design for pricing


Evaluation (2 months)


Award subject to FID


July. ‘14 Design


Finalisation 8 months


Detail design for construction


FID / NTP (March. ‘15)


Execute Contract Discharge


Requirement 10


Order materials and equipment Enabling works


Detailed Design


Complete March ‘15


Building Design Update Consult on Landscaping


Building Design Update Consult on Landscaping


Building Design Update Consult on Landscaping


2


20/11/2013 Diagram 1 – Grid Transmission Procurement © Crown copyright. All rights reserved. 2012 Licence number 0100031673. © EAOL 2013.