search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
20 VIEWS


You should advise [the client] when a project requires more specialist input, or has a significant subcontractor design package


Nigel Ostime, Hawkins\Brown


between reviews, which is not enough time to bring in benefits that the contractor is supposed to bring


• Watch out for time allocated to the Stage 4 design programme but based on the tender events schedule; this can give too little time for coordination.


Cost


The cost plan is often not made available, but try to get visibility of it, to be able to analyse it and determine whether it is realistic, and get cost under control. An initial cost plan that is based on Stage 3 can lead to Stage 4 design development (after the design should have been fully coordinated and frozen) and this can be difficult to explain to the client, so ensure early dialogue about what is legitimate design development and when the design should be fixed (ie at the end of Stage 3). Possible cost pitfalls: • Be wary of the need for coordination post tender and the contractor raising concerns over cost as a result


• Keep an eye out to check that the cost consultant is properly resourced and being pro-active


• Beware of provisional sums that push the design risk into the next stage and often end up being much more work when they are agreed later on.


Value engineering The programme for VE should be separated from the main flow of work and identified as a separate fee. As the onus is on cost, the VE/cost review programme needs to be integrated into the design process. There should be a final cost and a VE review/cost analysis period after the contractor cost is


WWW.ARCHITECTSDATAFILE.CO.UK UCL Queen Square Institute of Neurology and UK Dementia Research Headquarters © FTP


submitted. Trying to revisit packages already issued while you are preparing the next ones causes problems. The PCSA is effectively continuous value engineering, and there needs to be flexibility in the programme to allow for this. Programme in cost reviews for each package, and the process for agreement. Consider not just the additional work from VE but also the level of information needed, such as in the facade. Also, when agreeing performance or quality VE changes on their own (not as part of a coordinated solution), be aware that this could have an impact on later work when integrating into the developed design.


Change control


The change control process must be set up from the outset and be managed by the contractor. There must be clear definition of what is design development, and what is a change. Items not drawn in Stage 3 can be seen as a change, as they are not costed.


Coordination


Focus on coordination with MEP and structures, before package information is progressed. Difficulties occur where the planning application has been submitted without a fully coordinated design being developed, and this can lead to issues where the PCSA immediately follows on. Exercise caution and aim to submit sufficiently detailed planning applications with fully coordinated designs (you may need to


accept this is not possible if the client wants to minimise the scope of the pre-planning design activities).


Design information


Be wary of issuing a preliminary detail and the contractor taking it as final and making assumptions based on it. Sketches are the right way of illustrating PCSA proposals, to make it clear they are not to be adopted as the comprehensive solution. Include a ‘PCSA discussion’ watermark onto these types of study. Derogations which cannot be captured on official drawings need to be clear and concise; sketches or markups are better – written schedules often have grey areas, and ambiguities.


Separate teams need to progress the design and variations from the PCSA process; otherwise it will cause disruption. Note that QSs and contractors do not always understand 4a and 4b; it’s important to lay out the ground rules. In order to get the PCSA to work, all parties need to approach it as the buildability exercise it is intended to be, with an agreed programme and contributions defined from all parties. Architects and other designers should guard against the potential prolongation of PCSA periods, as it can take a lot of time, and therefore cost, to support them.


Nigel Ostime is partner and project delivery lead at Hawkins\Brown


ADF FEBRUARY 2022


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108