TENNIS
Centre Court sward after scarifi cation, prior to Attraxor application, seeding and topdressing
This change in our calendar necessitated a change in focus on our part, and as facilities were allowed to re-open post lockdown, it became evident that we would need to extend our member grass court season in order to increase the number of courts available for use. Firstly, because indoor facilities (which make up a quarter of our available courts) would be off limits, and secondly, because for large parts of the year doubles was not permissible, meaning that court capacity eff ectively dropped during these periods by 50%, as only singles tennis could be played.
Post renovation Poa
This need to create additional capacity meant that we needed to extend our playing season, fi rstly at the start of our season. We worked hard to ensure that as soon as restrictions facilitated a re-opening of tennis we would have grass courts ready, and this is indeed something we accomplished. It also meant stretching out the back end of our season, in turn pushing back our end of season renovations, thus reducing our window to complete works on the courts to ensure their readiness for the 2021 season. Whilst this was a trade-off
that had to be made, it created areas where compromises needed to be made. For one, could we risk heavy, invasive works if the courts would not then have time to recover prior to the winter?
For example, in a normal year, we would start renovating our centre court in early August, our three practice courts in mid to late-August, and then our four match courts sequentially through September, with the last two generally coming out of use in the last week of the month. With 2020 not being a ‘normal’ year, and capacity pressures mandating a longer grass court season, we put ourselves in a position whereby we would keep all eight courts open, including Centre Court, until the 1st of September, at which point we would start dropping courts out sequentially, but still leaving some in play until later in the month. That decision, whilst in the best interests of our members and therefore the club, did create some challenges. Most obviously that we would be condensing down works that we would normally spread over eight weeks into just four! This put pressure on manpower, especially as we were
One of my favourite pieces of advice to give to a
groundsman is to stop and think about why you are doing something; if you can’t explain why you are doing it, you almost certainly shouldn’t do it
88 PC February/March 2021
“
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132