search.noResults

search.searching

note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
East Anglia ONE Offshore Windfarm Construction Artificial Lighting Emissions Plan


September, 2016


HDD-08 HDD-09 HDD-10 HDD-11


HDD-12 HDD-13


HDD-14 HDD-15


HDD-16 HDD-17 HDD-18 HDD-19 HDD-20


23.


Cat 1 Cat 2 Cat 2 Cat 1


Cat 2


A12 Trunk Road Top Street Sandy Lane


Martlesham Creek and


Network Rail tracks south of Woodbridge


Waldringfield Road


Cat 2 Watercourse east of Howe’s Farm


Cat 1 Cat 2


Cat 1 Cat 2 Cat 1 Cat 2 Cat 2


Kirton Creek


Sewage works outfall watercourse


River Deben Queen’s Fleet


Landfall, Bawdsey Bramford Road


Grundisburgh Road


70 50


550 50


700 70


1000 60 50


55 55


110 55


55 55


160 55 55


The HDD technique is expected to be used at the majority of locations on the route where a trenchless method is required. This involves creating an access pit on either side of the obstacle to facilitate the installation of the drilling equipment and allow drilling under the obstacles, at an appropriate depth allowing the installation of the ducts. The HDD sites will have two access points, one either side of the HDD location, the drilling rig will be positioned on one side of the feature with ducting placed at the opposite side ready to be pulled back through the opening on completion of drilling.


24.


Once the cable duct installation is completed then works will commence on the installation of the EA ONE cables within the pre-installed ducting system. As the onshore cabling typically comes on drums of up to 1,300m in length, jointing bays will be required along the cable route to join each section of cable together. These jointing bays, approximately 10m long x 5m wide x 5m deep, will be constructed at regular intervals along the onshore cable route to allow cable pulling and jointing at a later stage. The joint bay with be excavated to size and a concrete poured floor with concrete or blockwork walls surround will be installed and topped with concrete slabs to leave ground cover to a depth of 1.1m.


25.


Further details on the construction methodology for the onshore cable route are presented in the Cable Method Statement (EA1-CON-R-IBR-021238).


3.1.3 Onshore Substation 26.


The EA ONE onshore substation will be located within a fenced compound (150m by 190m) to the north of the existing National Grid Bramford Substation. The substation will contain electrical equipment including power transformers, switchgear, reactive compensation equipment, harmonic filters, cables, control buildings and other associated equipment, which will largely be outside with a number of the components being within the buildings.


27.


The construction of the substation will include a number of key stages; include enabling works, foundations and building construction and equipment installation and commissioning. The enabling will include grading and earthworks to remove any unsuitable materials from the substation area and provide a level platform at an elevation of 56m AOD.Where possible, the materials excavated will be reused on site as engineering fill or landscaping depending on material properties. The enabling works will also include the construction of the main concrete access road.


28.


Following the completion of the site grading, works will commence of the excavations for foundation for the building and trenches to accommodate electrical infrastructure and installation of the drainage networks.


29.


The building is largely comprised of steel and cladding materials, with brick/blockwork at the base. The structural steelwork will be fabricated and prepared off site and delivered to site for erection activities using cranes. The composite cladding panels (e.g. Kingspan) will be delivered to site ready to erect and be fixed to the steelwork.


165 90 90


650


120 55 50


160


Page 9


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34