This page contains a Flash digital edition of a book.
19.6.1.1.1 Landfall


Scenario 1: Pre-installed ducts 71. One statutory designated site, Bawdsey Cliffs, lies within the landfall footprint. The sensitivity of the geological receptor at the landfall would be considered to be high, given its status as a designated site. Within Scenario 1 no trenching or HDD works are required but should the East Anglia ONE HDD works be forced to create a jointing pit in the intertidal zone a temporary ramp and haul road down to the base of the sea cliffs will be needed to secure access and construction of the East Anglia THREE jointing pit. If required, a temporary access ramp will be constructed over the top of the cliff and will be removable once works are completed. This temporary ramp will be located to the north east of an existing bridleway, where the Red Crag (for which the area is designated a SSSI) does not outcrop. Mitigation through design will mean that there will be no direct impact to the integrity of the SSSI feature. Given that the geological feature will be avoided, the potential to degrade the cliff face by trafficking, uneven loading and destabilisation during construction of the access ramp is considered to equate to a low magnitude of effect and the significance of the impact is considered to be moderate adverse. Additional mitigation is described in Table 19.17 below.


72.


The presence of a mechanical excavator brings with it the hazard of spills and leaks, although these are considered to be temporary (limited to construction period), of low magnitude (given limited volume of potentially contaminating materials) and reversible (as the temporary ramp/ haul road will be removed following completion of works). Beyond these works the need for excavation and interaction with the geology at the landfall is minimal and considered to be of low magnitude.


Table 19.17Mitigation measures for both scenarios Mitigation measures


In order to reduce the impacts to the underlying geology from haul roads, trenching, drilling and general construction activities including leaks and spills, the following mitigation would be undertaken:  Design and construct free standing ramp to minimise loading and destabilisation of cliff face;  Check and maintain equipment to ensure leaks and spills do not occur; and  Have spill kits available at all times and an incident response plan in place.


73.


Following implementation of the mitigation measures described above the magnitude of impact would be reduced to negligible, the overall significance of the impacts to designated geological receptors is considered to be minor adverse.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 19 Soils, Geology and Ground Condition Page 35


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58