MONITORING FOR OPTIMUM PERFORMANCE


While low carbon technology, such as Combined Heat and Power (CHP), can help cut energy bills, simply leaving the unit to run unmonitored is no longer a viable solution to sustaining long term cost savings. Gary Stoddart, Technical Sales Director at Remeha, explains.


CHP has a huge role to play in improving the efficiency of the UK’s commercial and public sector buildings. On-site CHP is approximately 30% more efficient than relying on traditional heating plant and electricity supplied solely from the grid.


CHP systems burn natural gas to generate heat, while providing electricity to supplement or replace the grid supply. This means that businesses can produce electricity at gas prices, which is cheaper than buying it directly from the grid.


With an energy cost ratio of around 3.5/1 (electricity 15p per kWh/gas 4p per kWh), the savings are calculated using the cost of energy input to the unit (natural gas), the value of the heat output (thermal) and the electricity produced.


Also, in comparison, CHP electricity doesn’t suffer transmission losses resulting from moving power over large distances, resulting in a more efficient process.


In addition to the cost (and carbon) savings, the end user enjoys a level of energy security from generating power and heat on site, close to the point of use.


However, for CHP’s potential to be fully realised, systems need to be carefully and correctly designed and commissioned. It’s important for all parties – including the CHP supplier – to be involved in initial discussions about system design. The Chartered Institution of Building Services Engineers (CIBSE) AM12 document urges designers to seek the advice of CHP suppliers ‘at an early stage of the design’.


The key to ensuring CHP is properly specified and delivers savings is to


22 | MONITORING & METERING


keep it as small as possible, and to remember that buildings with high and continuous, year-round heating loads - such as hospitals, hotels and leisure centres - achieve the most efficient operation.


If the heat demand is not present, oversized CHP will not run, and the anticipated electricity will not be generated. This also means that it’s not reducing the payback period and energy savings are being negated. In too many cases, the ‘10% for luck’ rule is applied, meaning that many buildings have larger plant than required. This not only increases the cost of capital expenditure unnecessarily, but also means that a CHP unit operates less efficiently.


When Remeha is assessing a site to see how feasible CHP is, we look at the base load for electricity and heat. For example, on an R-Gen 20/44 NG unit the heat produced is between 30kW and 44kW (based on an approximate heating return temperature of 30o


C) and the


electrical output is between 10kW and 20kW. If the base load is above these figures then the CHP will run continuously and the heat and electricity will be used in the building – which is the ideal. If the heat cannot be used, the site will either have to dissipate (waste) it or shut down the CHP.


While there is no minimal operational period per annum that must be met, it’s important to remember that if a unit is not running it’s not reducing the payback period and energy savings are being negated.


Ideally, designers need to consider running CHP 24/7, and storage is often the best solution – especially if a site has peak demands for hot water. The heat produced by the CHP


unit over a ten-hour-plus period can be stored in a preheat cylinder, and the hot water can then be used over peak periods.


It is also important for the CHP supplier to stay involved after commissioning – if they can monitor the system they can ensure it continues to perform efficiently and that it delivers savings.


A modem, connected to a landline or mobile network, can transmit data between the site and the CHP unit’s monitoring centre. The manufacturer will have the resource and expertise to analyse data in real time, and can provide guidance on how to solve any issues or alter the system to maximise performance, efficiency and cost savings. Knowing about any anomalies early can save the end user from significant losses due to unplanned system shutdowns, maintenance and repair.


If the CHP unit is being remotely monitored through a modem it will also inform the end user and the service team when a service is due.


Having said all of this, worryingly there are a large number of CHP units installed across the country that are not running as intended – something that could be easily rectified through early discussions about system design and effective, ongoing monitoring.


Cockermouth Community Hospital and Health Centre in Cumbria provides a good example. The original cottage hospital, which was almost 100 years old, was rebuilt in 2013, with the aim of accommodating all the town’s primary healthcare services under one roof.


A 5.5kW R-Gen SenerTec Dachs unit was installed to provide hot water for


www.tomorrowsem.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38