This page contains a Flash digital edition of a book.
Technical


chipping green was in a very shaded site, so it made sense to go with Poa there too. The challenge was to recreate the Poa sward without turf or suitable seed being available on the market. Time frame provided our final obstacle. It


was decided that the project would run from spring to the autumn meeting. With a start date of the 12th May, we would have until the 6th September before it needed to be performing at championship standard - just fourteen weeks for tree clearing, construction and grow in. As we were approaching the playing season, I felt that this was achievable.


The Design Process


As the club wanted a quick turnaround, we had to get started quickly. My role was to project manage, with Ricky Willison (our Director of Golf) designing the green and Weller Design providing architect drawings. The project was due to start after the spring meeting on the 3rd May, leaving four weeks to source and test materials. We chose European Turfgrass Laboratories Ltd (ETL) up in Scotland as our testing site. Ideally, the green should look and play as closely as possible to the other nineteen greens at Ealing (including the putting green) with the same grass species. It didn’t have to play to the standard of a USGA spec green, but must handle extreme wet weather; an increasing issue in the UK. As we would have around a twelve week growing in period, turf would be the easy option but, in my opinion, not a suitable one. Turf would look good on day one but, within weeks, you could go backwards. With the club expecting a top class green, I did not want to take the risk. Seed was another option that was not really viable. If we went with the traditional fescue/bent, it would not produce the required standard within the time frame. Creeping bent was definitely an option as it is a fast germinator and would produce the required standard, but it is a different species to the other greens on the course. Two solutions countered these issues. First, a


shallower rootzone than the 300mm standard used in USGA designs. A gravel layer would be added along with drainage, but the rootzone would sit at 250mm deep instead of 300mm. This is something that I had done before on previous projects, which not only saves money in time and resources, but also allows the rootzone more moisture. Perfect for Poa! Second, cores. Over the years, I have


Over the years, I have implemented turf nurseries and made several tweaks on existing greens using Poa cores instead of imported seed or turf. These worked extremely well. However, I had never created a full green with this method





implemented turf nurseries and made several tweaks on existing greens using Poa cores instead of imported seed or turf. These worked extremely well. However, I had never created a full green with this method. What I had seen was how well Poa cores had done in terms of germination and performance. The other great advantage was that a Poa cored green would look exactly the same as other greens already on the course. So, with the rootzone depth set (and tested by ETL) and the Poa core method confirmed, we were ready to go!


Construction


As the golf season would be in full swing, we decided to use some external labour for the construction and site clearing. I’m usually really keen for clubs to do construction jobs in house but, without that option available, we selected people that we’ve worked with before; people that I know do the work to my standard. Work started on the 19th May. The first task


was to fell all the trees, which was done within two days by our external tree surgeons, Moore Trees. As soon as the last tree came down, some external spoil was brought in to create the green’s shape. Once all the spoil was laid, Oliver Flanagan


(who has worked with me on other projects in the UK) did the grading and shaping. It was decided that the grass surrounds should be to


the same standard as the green itself, so irrigation and drainage pipes would be installed and a 50mm ‘sand carpet’ would be laid in this area to help with performance. We were now two weeks into the project. Our main aim was to get the green finished as early as possible, so that we would have an extended time for the grow-in, which would be tight anyway. On closing at the end of week two, we had


the trees felled, green shaped, materials added and irrigation and drainage laid. We were ready to lay cores on the 2nd June.


Core laying As the new green would be 300m2


in size, we


knew that we would have to use the main greens as the source for the cores. We were now officially into the playing season, with societies booked and competitions in play, so it was far from ideal. But the club wanted this green playable as soon as possible, so there was no other option. My first estimate was that we would need


three or four greens for the cores. That seemed manageable in terms of returning the course back to standard very quickly. However, it quickly became apparent that we would need to use rather more greens. In total, eight greens had to be hollow cored, each needing a recovery plan afterwards. The membership weren’t entirely happy about it, but the additional facility was worth it in the end! To get the cores, we set our verti-corer with 12mm tines going down 50mm deep on a 50mm square pattern. We started laying the cores on the 2nd June and, as I was keen to do it in one day, it required a big effort by the greens staff. The cores were laid out around 25mm thick.


They were spread evenly across the green and raked out. Once laid, I decided to apply creeping bent A4 seed set at 2g/m2


as back-up,


just in case the Poa didn’t take the way I wanted it to. I need not have worried! At the end of that first day, the cores were down and seed sown. To finish it off, we gave it two rolls with a hand mower, using just the metal roller at the back. It looked pretty good after that!


Grow in


All the hard work was now done and the project entered the grow-in phase. Anyone who has experienced a grow-in will tell you that it can be just as intense as construction - and as important. From my experience, the


Area cleared in two days


External soil brought in PC FEBRUARY/MARCH 2015 I 111


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148