CABLING ON WINDFARMS


Cable trenching is an essential part of works performed on a windfarm project. The majority of windfarms are constructed in areas that are not suitable for general agricultural development. Therefore, the topography of the routes designated for the cable can be rugged and unforgiving and pose challenges for access of materials and plant.


ADAPTING TO NEEDS


Cleantech Civils Ltd has formed its company foundations primarily from


trenching and utility laying. Over the years, it has developed plant and equipment to adapt to the need for more efficient ways of trenching, unique to the industry.


Large capacity cable drums and ducting trailers have proved to be a success in increasing production on site while maintaining quality assurance and safety of materials. Crossing existing waterways, roads and ravines always pose a challenge, but with the aid of Cleantech’s directional drilling department, sleeve construction and fluming methods, it can be carried out without disruption to the surrounding environment.


CABLING PROCESS OPTIONS


The process for installing cables from the turbines to the connection points can be carried out in two ways, either by direct bury or through ducts. The direct bury process involves taking the cable directly


from the drum into the excavated trench. Cleantech designed and developed a frame which can carry three cable drums and a fibre optic drum and mobilised along the route using the 45ton excavator. The advantages with this method are all the cables can be laid into the trench on one passing, and from a Health and Safety benefit, no operatives are required to enter the excavation as all placing and cable tying can be completed safely from the sides of the excavation.


DUCTING PROCESS


The ducting process is used more typically on spine routes and in roadways. The company use excavators with rotator/ swivel hitches and 0 tail swing to assist working in difficult narrow routes. All their staff are highly experienced in constructing to the specification of cable ducting, traffic management, safe-dig systems and environmental awareness.


They have also designed a duct laying trailer where teams can place duct safely into the trench from high level which also improves efficiencies and safety.


After ducting has been successfully installed they place the cables into each configuration with specialist pulling equipment, all calibrated and certified to pull the cables to specification.


Print outs and data history can be presented for all cable pulls throughout the project.


Cleantech Civils Ltd www.cleantechcivils.com


REDUCED COSTS


The design typically reduces the total rebar and concrete contents of a base by 20% each, which also affords associated labour savings and a shorter construction programme.


Peikko


www.peikko.co.uk = Click to view video


www.windenergynetwork.co.uk


97


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108