MOVING THROUGH THE GATED PATH: NCOE’S PROCESS FOR PROJECT DEVELOPMENT AND


In our previous article in the May/ June 2012 edition of this magazine we looked at Project Strategy and how it was important to assert an early influence on a project. This identified how influence and cost are all related. However in this article we will demonstrate how the gating process maximises influence at the front end of the project and ultimately lowers financial and other risks.


SUCCESS AT NCOE OUR GOAL IS TO GENERATE BUSINESS VALUE BY DELIVERING PROJECTS, WHICH ARE EFFICIENT IN BOTH CAPITAL INVESTMENT AND LONG-TERM OPERATION


Our processes in NCOE have been developed from a wealth of industry experience which exists in the company. They also represent the current view of recognised good engineering practices. We apply these consistently across our range of projects. And, of course we are always looking for new projects and developments in which we can help in this way.


MAXIMISING INFLUENCE BY FOLLOWING THE GATED PATH We apply a gated process to our projects to ensure all options are properly screened and the correct option is selected for definition and execution phases.


A gated process has a clearly defined entry point and a clearly defined exit point. This means that in a project lifecycle you cannot move forward, progressing into the next stage until the first gate has been passed and approval has been gained to move forward. It really is a bit like going on a walk entering one field, walking through it to reach the gate at the other side. Design-readiness and understanding project risks are major factors at gate milestones. More often than not trying to push forward with a design concept when the project risk are not fully understood usually results in re-work later in the life cycle. Therefore a gated process minimises these risks.


One of the major advantages is that it ensures there is a methodical process and audit trail to each decision. The prize is selecting the correct option first time without having to go back and recycle options. Recycling is a very costly and time consuming process. Therefore time and effort spent in the earlier stages of the life cycle presents significant gains later on. For example changing the installation methodology before you start costruction is much easier than when you are at the workface with a team of construction personnel.


YOU MAY RECALL THE GRAPH THAT WE INCLUDED IN OUR PREVIOUS ARTICLE. DEMONSTRATING COST AND INFLUENCE AT EACH STAGE OF THE PROJECT:


The same cost and influence is applicable to the gated process.


94


www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108