This page contains a Flash digital edition of a book.
Chemical Focus


Boost in efficiency for chemical distribution company


Control panel continuously monitors the pH readings and records them along with the effluent discharge flow rate.


F


or a company involved in chemical storage, manufacture and distribution, the relationship with the local water authority is understandably well established. It was required to provide regular pH and flow readings for its discharge of effluent, however this had become a very time consuming and inefficient exercise. The end of life equipment was in need of


replacement and improvement at the same time; a task that required expert knowledge of both design and installation.


As a company that takes its responsibilities to the environment very seriously, chemical distribution company Brenntag decided that a new system was required that would provide automatic pH readings, pH adjustments and flow readings – all of which could be logged and reported to the local water authority. Furthermore, possible improvements were


also identified with the batch control systems for producing sodium hypochlorite, sodium hydroxide and hydrochloric acid. These systems also needed to be replaced with a design that improved efficiency and productivity. The entire project was awarded to Bürkert Fluid Control Systems. Originally, the effluent plant on site had to be visited


twice a day by an engineer to manually measure the pH as well as the tank levels. Once these readings had been established, the engineer had to determine how much hydrochloric acid or sodium hydroxide (caustic soda) to add to the tanks to balance the pH readings. This was a very time consuming exercise and far from being efficient. In addition, the local water authority was also


looking to improve the monitoring of discharge levels, which would require further support from the onsite engineer if the original equipment was maintained. Having made the initial site visit to establish the


scope of the project and established the design criteria, Bürkert designed a complete system that included pH sensors and level sensors in the tanks as well as on/ off valves for the chemical dosing equipment and flow sensors on the discharge pipe work. This was all controlled by a bespoke, custom-built panel that included a PLC and an HMI. The control system was specifically designed for Brenntag and the software specially written to meet the client’s specifications. Once the designs had been finalised, the installation


Fig. 1. The control system was specifically designed for Brenntag and the software specially written to meet the client’s specifications.


64 www.engineerlive.com


process could begin. Working closely with the site maintenance team, Bürkert was able to install the new equipment without disrupting the production process and also ensuring that all the necessary records for the local water authority were maintained. This did entail some out-of-hours working, but the end result was an updated and improved control system, which incorporated the latest design and components to ensure long service life.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68