Meeting grouting challenges


Ted Allan, Harvey Lee, Barry Robinson and Colin Reilly report on a grouting equipment system developed to meet a difficult offshore task.


subsequent platform stability, was the requirement for multi-compartment under base grouting, using a special ‘flexible’ grout formula, which had to be completed within a tight 72 hour period - the expected maximum ‘weather window’ providing suitable conditions for the grouting vessels and crew to operate safely.


T


An estimated 6100cum of grout (comprising cement, sodium silicate and sea water) had to be pumped into the 17 underbase compartments, via a manifold control panel to an extensive piping system, in a continuous operation over the 72 hour period. ULO Systems was contracted to develop a


grouting equipment system that could perform the above task. Tis system needed the capability to store 2260 tonnes of cement, and 360 tonnes of liquid Sodium Silicate, house and operate all required equipment, and deliver the specified mix and quantities on a continuous basis to complete the installation successfully within the specified timeframe. In order to provide enough storage for the 2260 tonnes of cement, ULO had three new 100 tonne capacity horizontal silos fabricated, and these were used together with a series of 40 tonne, 50 tonne and 100 tonne existing units as well as vessel inboard P tanks to achieve the required infield storage capacity. All of the required equipment (except for some of the silos) had to be housed on a DSV including 100 per cent redundancy on all operating equipment. ULO set about developing a mixing and pumping system, based around conventional technology, which would not only have the required capacity to perform the work, but would also, be in modules which were transportable by conventional road transport and sea freight, and, fit into the confined deck space available on board the DSV. Tese


he latest Arkutun Dagi Gravity Base Platform was installed in 35m of water in the Sakhalin field, Russia, in mid 2012. One of the main issues, critical to the success of the installation and


space limitations presented an additional challenge to the ULO team, particularly because 100 per cent contingency equipment capability had to be available for immediate operation if required. Although grout mixing/pumping equipment of sufficient capacity was available in the market, they were physically too big to fit into the available space on the vessel, so ULO had to design and build new modular units which would, when assembled, work in unison with the RJM (Re circulating Jet Mixer) to ensure continuous mixing and grout delivery, and still fit inside the available deck space footprint. Te functionality of the system was dependent upon the RJM having a mixing tank of the correct size so that the vortex action in the mixer tank was maintained, which was critical to the efficient mixing of the seawater, sodium silicate and cement in sufficient quantities to meet the demand and on a continuous basis, whilst coupled with the high capacity delivery pumps.


Te set up was also fitted with a sophisticated quality control system which incorporated non nuclear densitometers, and a series of flow meters, which were linked back to the Quality Control room via a computer linked data logging system. After a detailed technical evaluation and design effort, ULO built and tested the system successfully


www.engineerlive.com 21


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100