This page contains a Flash digital edition of a book.
Standard Product standard EN 15650:2010 Fire dampers


EN 12101 Smoke and heat control systems


Test standard


Classification standard


EN 1366 Fire resistance tests for service installations


EN 13501 Fire classification of construction products and building elements


Standard for variations from tested applications


prEN 15882: Extended applications of test results for fire resistance tests for service installations


Table 1: Principal European standards regulating fire dampers


BS EN 1366, and unlike the previously employed BS 476 procedures, this standard contains test procedures that are attempting to ensure dampers are installed in ways that are clearly consistent with the regulated and tested installation detail.


Fire damper testing Figure 2 shows a simplified layout for a BS EN 1366 test that, in this case, is designed to assess the ability of a fire damper to withstand heat and prevent the passage of smoke and gases at high temperatures in a horizontal duct. The damper is installed into the furnace wall and a plenum is fixed to the face of the damper, leading to a fan that maintains a set subatmospheric pressure on the face of the damper during the test. The damper is opened and closed 50 times (based on two maintenance checks per year, nominally simulating 25 years’ service), prior to the fans or fire being started to test mechanical robustness and then left in an open position at the start of the fire sequence. If a leakage test is to be undertaken, the damper is closed and the leakage rate measured using the measuring system in the test duct at ambient conditions prior to the fire test. The damper is then set to a position to give a velocity of 0.15 m/s across the face of the damper, the furnace is started, and the damper blades must fully close automatically within two minutes. The damper is then subjected to a required subatmospheric pressure and temperature of 1,050°C to 1,150°C for two to four hours. Leakage (S) is leakage during the fire test of less than 200 m3


h-1 per m2 of damper face


area, measured at ambient temperature. This is the same requirement for all sizes


60 CIBSE Journal September 2012


of manufactured dampers, and so can be particularly demanding for a range with small size dampers. Integrity (E) is the time that a damper allows a leakage less than 360 m3


h-1 per m2


without a failure. This would normally be associated with smoke dampers and the fire performance of a fire and smoke damper. Insulation (I) is the average temperature rise on the unexposed face to 140°C, with a maximum point value of 180°C. The rating will reflect the performance of


the damper – for example, ES 240 would indicate a damper that has been tested for both integrity and leakage and has maintained performance to standard requirements for four hours. (Historically, the UK has used the format ‘ES 240’, but under EN 13501 this will be shown as ‘E240S’.)


System design System design and installation for fire and smoke dampers must be project-specific, taking into account up-to-date legislation and manufacturers’ recommendations. So while it is important to ensure that appropriately certified dampers are used, it is as critical to install those dampers so that


Furnace Fitted fire damper Plenum


they reflect the conditions in which they were tested and assured. This requires close liaison between manufacturer, designer and site workers. Consideration must be given not only to damper installation, but also to access for maintenance and testing during the lifetime of the building. The key tasks for successful fire protection in a building, as identified by DW/145, are: Fire/smoke compartmentation – A fire strategy should be established and recorded that clearly shows fire and smoke compartmentation and the details of the protected areas. System specification and design – Those responsible must ensure that the design and application is suitable for the particular project and not simply generic. Programme of activity – This includes the relationship with other trades, and the physical position of the damper in relation to the building fabric and other services. Damper procurement – All the appropriate specifications for dampers must be supplied by the designer. Substitutions for dampers other than those specified require checking by the designer.


Dilution control used to adjust duct volume flow and pressure


Fan


✔Part 2:1999 Fire dampers


✔Part 3:2005 Classification using data from fire resistance tests on components of normal building service installations


✔Part 2: in approval process Dampers


Fire (and leakage) rated dampers ✔


Smoke-rated dampers


✔Part 8:2011 Specification for smoke control dampers


✔Part 10:2011 Smoke control dampers


✔Part 4:2007 Classification using data from fire resistance tests on components of smoke control systems


Horizontal or vertical barrier of similar form and orientation to that used in built environment


Measuring system


Figure 2: A simplified representation of the setup for testing fire dampers to BS EN 1366 www.cibsejournal.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80