Ports & Terminals airborne dust.
Martin Engineering supplied other redesigned components to contain material and improve serviceability. Belt support cradles were installed under the drop chute to absorb impact and stabilize the belt line and prevent spillage. AES also mounted EVO External Wearliner on the load zone’s existing skirtboard for improved sealing. Because it is attached from the outside, it is easier to install, inspect and adjust than conventional seals, without requiring confined space entry.
Results
ABOVE: With the new conveyor Load Zone from Martin Engineering, the terminal has increased the average load rate for the entire ship- loading process from 700 mt/h to 858 mt/h
steps to increase throughput at the port facility, but initial efforts to reach 2,000 mt/h proved almost entirely unsuccessful. “Working with what we had, we could only reach 600-700 mt/h,” said AES Terminal General Foreman Vic Stoltz. “We made some improvements and got up to a steady run rate of 750 mt/h. But there were still some major issues with coal backing up in the chute.”
Even as some gains were realised, AES found that with
higher-speed operation, dust became an increasing problem. The ship loader wasn’t designed to contain fugitive material, and airborne coal dust generated negative attention, threatening community relations. The company reports that the recent chute upgrades have virtually eliminated spillage and dust issues.
Combining solutions
The need to increase throughput at Seward while protecting the region’s air quality and natural splendor led AES to investigate new conveyor technology from Martin Engineering. After testing the Usibelli coal to determine its flow properties, Martin specialists used Discrete Element Method modeling to design a chute capable of properly handling the coal.
“When we got back the computer models, we saw that we were able to pass 1500 mt/h and still control dust, all while keeping within our capital budget,” said Stoltz. “When our management realised that we could increase throughput, increase safety and reduce our environmental impact all at once, they were completely in favour of implementing the suggested upgrades,” he recalled.
A new conveyor architecture
The new transfer point makes use of Martin Inertial Flow Transfer Technology, the entire chute custom-engineered and modeled in 3-D to provide the optimum design for the material and flow rate needed. The “hood” controls the flow of material from the discharging conveyor, maintaining a coherent material stream and minimizing induced air. A smooth loading chute (“spoon”) places the stream of coal onto the ship loader’s boom conveyor at the proper speed and angle with minimal impact, reducing material degradation, belt abrasion and the expulsion of
www.solidsandbulk.co.uk
The first thing the AES crew noticed was an improved material load rate. During the initial shakedown run, operators noted the conveyor’s weigh scale pegged at 100%, but the belt didn’t shut down. The old system peaked at 1000 mt/h (including ship and hatch moves), but with new components in place, the system now hits peaks of 1500 mt/h. “We don’t have slowdowns due to the chute clogging up, which previously was a constant battle,” Stoltz added.
Equally important, following the system’s initial run, the ship loading area was virtually free of fugitive material and dust build- up, allowing AES crews to reduce their cleanup time from days to just hours. “The clean-up time has been reduced by more than 40 man-hours per shipload,” said Stoltz.
Reducing risk To AES, the environmental and worker safety benefits of Martin Engineering’s upgrades have been just as important as the production advantages. “Faster loading times help manage our risk, from both the environmental and safety perspectives,” commented Bart Coiley, AES Manager of Environmental Affairs. “The longer it takes to load a ship, the greater the chances of creating dust.”
Summarising the experience, Denton said: “The work that Martin Engineering did eliminated a chronic bottleneck for us. There were many things we were doing to increase our throughput, but it was impossible to realise the full benefits until we cleaned up our loading operation with the installation of the new EVO hood and spoon transfer chute.” Stoltz added: “With these upgrades, we’re earning our money back every time we start it up.”
For more information visit:
www.martin-eng.com or email:
info@martin-eng.com
ABOVE: To improve flow and reduce the escape of dust and spillage, Aurora Energy Services authorized improvements to the ship loader’s boom conveyor
November 2010 • Solids & Bulk Handling 11
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60