This page contains a Flash digital edition of a book.
Fire station retrofit Case study

Data

Fire station’s projected improvements

Design consultant: Scott

Wilson

M&E Engineer: JSMS Ltd

Total project cost: £1.3m.

Fuel savings of £7,200 a year predicted

Display energy certificate:

projected improvement from D90 to B25

Boilers: two 45 kWh biomass boilers with a 600 litre thermal store provide all heating and hot water

Overall heat load:

expected to fall from 425,000 KwH to 86,200 KwH. All energy use to be compared against historic data

Lighting controls: high

frequency lamps with occupancy and daylight control in all areas of the building. Expected to save 30% of electricity load

Insulation materials: in

both the walls and roof. Chosen for their minimal environmental impact with zero ODP and low GWP

Photovoltaics: 14.4kWp

of PV mounted in four strings on the appliance bay and main building roof. Currently contributes 6% to 7% of electricity, short of eight per cent projected, with shortfall attributed to poor weather

Windows: double glazing with low emissivity glass

Projected improvement in U-values (W/sq m K):

Roof: 2.502 to 0.24 = 90% Walls: 1.58 to 0.548 = 65% Cladding: 2.37 to 1.2 = 49% Windows: 5.7 to 1.2 = 78%

>

Photovoltaic solar cells on the roof provide about 7 per cent of the station’s electricity needs.

Photovoltaics

Conventional electricity supplies have been supplemented with 14.4 kWp (kilowatt peak) of photovoltaic (PV) cells mounted on roof areas of the fire station. Shaw hopes the cells will provide 8 per cent of the station’s annual electricity consumption, although he admits that the current contribution is closer to 6 to 7 per cent, which he blames on poor weather. The existing Automatic Meter Reading for electricity

has been supplemented with remote logging of the PV system, so that comparisons can be made between predicted and actual outputs in real time. A grant of £40,000, half the total cost of the PV

system, was obtained through the government’s Low Carbon Buildings Programme. Shaw admits PV is expensive but argues: ‘On a fire station you want something simple that no one has to bother with. There are no maintenance costs; you put it on the roof, plug it in and it works.’

Insulation

While the London Fire Brigade is enthusiastic about renewable energy, Bentley would advise anyone attempting a low-carbon refurbishment to focus first on insulation and air tightness: ‘It’s the most effective thing you can do.’ The U-values of the roof have been improved 90 per

cent, from 2.502 to 0.24 W/sq m K, while the walls, to which cavity wall insulation was added, have improved 65 per cent, from 1.58 to 0.548 W/sq m K. The U-value of the cladding that covers several of the station walls has improved 49%, from 2.37 to 1.2 W/sq m K. Bentley says extra insulation was added, above and

beyond the original design specification, to voids in the wall cladding that were discovered as the building work progressed. ‘Obviously you end up with a bigger bill, but you won’t get another opportunity to do it for 30 years, so there’s no point leaving it,’ Bentley reasons. The U-values of the windows were improved 78per cent, from 5.7 to 1.2 W/ sq m, after single-glazed, wood-

38

CIBSE Journal April 2010

and-steel windows were replaced with aluminium- framed, double-glazed windows made with low- emissivity glass.

Materials

Bentley tried hard to use materials with low embodied carbon and consulted the University of Bath, which publishes a free online database of embodied energy and carbon for building materials (https://wiki.bath. ac.uk/display/ICE/Home+Page). He was mostly successful; the only high-carbon element in the Croydon refurbishment is the aluminium frames for the windows and the rainwater cladding on the walls, he says, although he rues the fact that there is no low- energy glass available currently. Bentley is frustrated by what he sees as secrecy

and obfuscation among manufacturers on the issue: ‘There is no pressure on the industry to bring down the embodied energy in its products. Manufacturers will not tell you how much embodied carbon is in them.’ Following the refurbishment, Shaw is hoping to

achieve an improved display energy certificate (DEC) rating of B25, compared with D90 before the work started. He calculates that the building’s overall heat load has been cut from 425,000 kwH down to 86,200 kwH, based on the new U-values compared with the previous ones. Bentley explains that the projected savings are based

on the actual heat requirements of the old building, measured using the metered gas supply to the old heating boilers, including an assumed percentage efficiency, compared to the new heating requirements for the new insulated buildings. These figures were compared with the results from the SBEM calculations to give a reality check. Shaw will be monitoring the results, using the

automatic meters for the electricity and biomass boilers and comparing the data against the historic data on gas and electricity usage. ‘I have personal targets to make sure these things work,’ says Shaw. l

www.cibsejournal.com Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84
Produced with Yudu - www.yudu.com