DRILL & BLAST | TECHNICAL


On top of the hardware layout, the Mobilaris system


then runs its suite of software products that have proved their effectiveness in underground mines. The modules available from Mobilaris Tunneling Intelligence are Planning and Scheduling, Productivity Analysis, Situational Awareness, Emergency Support, and more. “We have adapted and developed them to fit the


specific needs in tunneling construction,” says Bolsöy. In effect, it is a real-time overview of the network of


resources deployed and in action. It shows how progress is being achieved across the faces and headings, and the performance of the supporting supply lines. When Epiroc acquired Mobilaris Mining & Civil


Engineering, in 2021, Bolsöy also transferred with the business. Serving mines first – across the world – Epiroc’s Mobilaris Mining & Civil Engineering business has expanded into the tunnel construction sector, “initially in northern Europe but requests are being received already for projects elsewhere,” he says.


SAVINGS FROM DATA Through recent discussions with a tunneling contractor, Bolsöy says, they were able together to specify “the typical timing of the drill and blast cycle, including typical and very often occurring delays.” This means


how long the delay is per round, on average, “and how often they typically occur.” On these “very interesting” points, he says the detailed


discussions determined the specification for the average delay per round to be approximately 10%-15% – which “means 1.5 hours are added if a round was 10-hour (excluding injection), which is a lot of time waste.” A rough estimate for potential time saving in tunneling


works can then be calculated by including an average advance per meter per round. For example, based on the judged figures, then a


2km-3km-long (1.24 miles - 1.86 miles) tunnel could have the tunneling period reduced by about one month, he adds. On top of that is the potential for cost saving, adding either an hourly rate or average rate per meter of advance. “Adding other activities may even further improve the


potential” for benefits from savings, says Bolsöy, and he sees Epiroc’s Mobilaris Planning & Scheduling tool as offering potential on these points. The tool helps a customer “see what’s going on in


real time,” he says, and “how to easily adjust timing of the next activity in the cycle” – including actions such as when to, more accurately, order the shotcrete, etc. Often this is a key point of delay, he emphasizes.


Above left:


Real-time data collection automatically and by input in tunnels


Above right:


Epiroc’s Mobilaris business brings its real-time data logistics to tunnels


Below left:


Operator Client on tablet during tunnel operations


Below right: Planning & Scheduling


Spring 2023 | 45


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53