search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
TRENCHLESS | RED RIVER VALLEY


Right, figure 4:


Minger lowering the EPBM into the launch shaft for Contract 5a


creeks, highways, a BNSF railroad, and a gas pipeline.


This contract will be divided into two, 12.5-mile segments of 72-inch diameter steel pipeline: Contracts 6a and 6b. Contract 7 constitutes ~13 miles of 72-inch diameter


steel pipeline spanning from approximately 7 miles west of Cooperstown to approximately 3.5 miles east of Cooperstown, near the discharge structure at the Sheyenne River in Griggs County. Contract 7 is evaluating the design of 20 trenchless crossings of wetlands, creeks, roads, and railroads.


RRVWSP TRENCHLESS INSTALLATIONS Across Contracts 5 through 7, 39 trenchless crossings spanning 7,325-linear feet have either been constructed, are actively being installed, or are in various stages of design as shown in Table 1. Trenchless installation facilitates the delivery of this pipeline while reducing disturbance of sensitive wetlands and creeks as well as preventing the interruption of service on highways, railroads, and utility lines.


TRENCHLESS BORING MACHINES Trenchless solutions are employed to meet to the frequent challenge of constructing and installing linear conveyance infrastructure in ground conditions where traditional cut and cover methods are either not feasible or may be detrimental to sensitive environments. For the RRVWSP program, construction in varying ground conditions was possible due to advancing technology in tunnel machine manufacturing – specifically, slurry Microtunnel Boring Machines (MTBM) and Earth Pressure Balance Machines (EPBM) were leveraged to execute this work.


32 | Fall 2023


MTBMs For Contract 2, a slurry MTBM was employed to directly install the conveyance tunnel from the wet well shaft to the intake structure in the river using a one-pass system. A jacking frame in the launch shaft (Figure 3) applies pressure to the casing pipe which advances the MTBM, which in turn advances the pipe alignment. Additional pipe segments are connected and jacked into place from the launch shaft as the MTBM progresses forward. Slurry lines are also extended to facilitate continuous


muck removal. A guidance system within the MTBM is employed to assist with installing pipe to required line and grade tolerances. This process continues until the MTBM reaches the reception shaft. Once the MTBM reaches the reception shaft, the MTBM is removed, and the process of making connections to existing structures can begin. Slurry MTBMs are applicable to coarse-grained


ground with high groundwater conditions, such as those anticipated in Contract 2.


EPBMs For Contract 5a, an EPBM was employed to construct the trenchless crossing beneath the railroad and highway to minimize environmental impacts and disturbance to existing infrastructure (Figure 4). Like the MTBM, the EPBM also utilizes a jacking frame to apply pressure to the pipe segments to advance the alignment as the machine excavates forward. EPBMs are more suitable for fine-grained, or clayey


ground, which can be conditioned to turn the excavated material into a fluid that balances the pressure at the face of excavation. Without the need of a dedicated


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57