Power from waste |
Avertas Energy: Australia’s first large-scale thermal waste-to-energy plant
Left: Avertas Energy site as of December 2021 Right: Visualisation of the completed plant
While the concept of waste-to-energy is well established in many countries, Australia is not one of them. However, this is about to change. As the picture above shows, the Avertas Energy WtE facility in Western Australia – described as “the first facility in Australia to integrate recovery and reuse of waste with the generation of electricity” – is taking shape.
Located in the Kwinana industrial area, about 40 km south of Perth, Avertas Energy will process around 486 000 tonnes per year of residual (post recycling) MSW (municipal solid waste) – which would otherwise be sent to landfill – and deliver 36 MW of baseload power to the grid. It will also produce ash byproducts useable as construction materials, and recover over 6000 tonnes per year of metals not normally recovered by other means.
As well as MSW, the plant will also be capable of processing commercial and industrial waste and construction and demolition waste. The waste will be sourced from a range of sources including local councils in the Perth metropolitan area. The project has the ability to generate large scale generation certificates (LGCs) for eligible feedstock in accordance with Australia’s Clean Energy Regulator requirements.
The A$700 million waste-to-energy facility will use Keppel Seghers air cooled grate technology with vertical boiler, a design configuration that
aims to achieve efficient energy recovery and good operational reliability.
Keppel Seghers technology may not have been previously used in Australia but it is employed in more than 2000 facilities globally, including more than 100 waste-to-energy plants in 18 countries. Keppel Seghers, which is providing the technology under a EUR 70 million contract – the scope of which includes the core equipment, design and technical services for the plant’s furnace, boiler and flue gas treatment equipment – is a member of the Keppel Infrastructure group, the environmental technology arm of Singapore- based Keppel Corporation.
The Avertas Energy plant is being built by an EPC consortium led by Acciona (designer and constructor) and will be operated under a 25 year O&M contract by Veolia, which already operates over 60 waste to energy plants globally. The steam turbine for the Avertas Energy facility – a 45 MW DST-G20 single-body type – is being designed, manufactured and delivered by Pilsen-based Doosan Škoda Power, which will also be responsible for providing technical assistance during assembly and subsequent commissioning of the facility.
Doosan Škoda says Avertas is its first contract in the Australian market and sees it as a “stepping stone to other planned energy-from-waste projects in Australia.”
The Avertas Energy project was initiated by Phoenix Energy as long ago as 2009, and subsequently co-developed with Macquarie Capital.
In October 2018, it was announced that a consortium comprising DIF (Dutch Infrastructure Fund), Macquarie Capital and Phoenix Energy Australia had achieved financial close on the project, with DIF acquiring a 60% shareholding in the project (through two of its funds: DIF Infrastructure IV; and DIF Infrastructure V), the other main shareholder being Macquarie. On financial close, Avertas Energy, a joint venture of Macquarie and DIF came into being as the owner of the project.
Macquarie and DIF have provided $A275 million of equity finance, while a group of financial institutions and the Australian government’s Clean Energy Finance Corporation (CEFC) have provided $A400 million debt finance, with CEFC committing up to $90 million towards the project. In addition, the Australian Renewable Energy Agency (ARENA), also a government entity, contributed a grant of $23 million towards project development.
The Avertas Energy facility is expected to be the first of a number of waste-to-energy projects planned in Australia, which is estimated to produce more than 23 million tonnes of municipal solid waste annually. In developing the Avertas project, Phoenix estimated that, “on average, a wheelie bin placed on a verge for collection contains enough waste to produce up to 14% of a household’s weekly power needs.”
Left: Chimney sections, combined weight 500 t, total volume 6000 m3
, for the Avertas
waste-to-energy facility being loaded on to AAL Nanjing heavy lift multipurpose vessel, end September 2021. The sections were manufactured and loaded in Humen, China, and shipped long-haul via AAL Shipping‘s Asia–West-Coast-Australia monthly liner service to Henderson, Australia
30 | January/February 2022|
www.modernpowersystems.com
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45