REGIONAL REPORT Ӏ MIDDLE EAST


Al Faris was commissioned to set a 207 tonne generator and a 115t HP turbine on its foundations. To do this Al Faris used its 1000 tonne capacity Liebherr LR 11000 lattice boom crawler crane with a SDWB2 configuration and a 66m main boom and a 48m luffing jib. Also at the Al Warsan 2 plant


waste per year to generate 200 MW of sustainable electricity. It initially opened in the second quarter of 2020, although development is ongoing, and other waste to energy plants are being built around the country proving a fruitful source of work for crane rental companies. In 2022, at the Al Warsan 2


j site, UAE-based crane rental firm


Johnson Arabia’s tandem lift of the gates to Expo City Dubai


NFT Group


worked with Yongmao to provide four custom luffing jib tower cranes on the Al Warsan 2 waste to energy plant


NFT Group worked with Yongmao to provide four custom luffing jib tower cranes. The technical and time requirements for the required tower crane were too high for any available local manufacturer, so cranes and construction specialist NFT Group contacted Yongmao Holdings and the two companies worked closely to make the required customised tower cranes in the short period of time available. Four cranes in all were involved.


Two were STL4200 models, with 62.5 m jib, 88 m height and 100t capacity, mounted on travelling chassis; two were STL2400 models, with 70 m jib, 74 m high and lifting 80t, on static fixed bases. Manufacture took around six months including shipping. The


cranes arrived on site in March 2022. The programme was to install the tower cranes in 25 days but NFT group managed to reduce that by 50% to complete the installation in record time. The STL 2400 was meant to be installed in 18 days but NFT completed installation in just a week. The larger STL 4200 was expected to take 25 days to install but the NFT Group managed to reduce that to 12 days. To achieve this, two fully-dedicated teams supported by a supervisor from the OEM, worked 12 hours a day. While one team off-loaded and assembled, the other team erected the assembled parts. Three mobile cranes were on site to cater to these simultaneous activities. NFT Group also provided the site with monthly preventive maintenance and a dedicated technician on site 24 hours in case of emergency.


STEAMING AHEAD At another new waste to energy plant in Dubai Al Faris was commissioned to install a


f


22 CRANES TODAY


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53