search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
RAIL PROJECTS - HS2 | TRANSPORT


gathering, for sharper analysis, pale in comparison to those years still to go before trains run. Blame for the schedule delay was put down to two


problems: first, civils slippage in the past (estimated one-third complete versus two-thirds planned (according to the last usable baseline schedule, B 7.1); second, too little time was allowed for the extensive and expensive non-civils works and equipment to fit-out the line and have the fleet of rolling stock. This is all with respect to tunnel works outside


central London. Within the centre there is the last leg of the line, to link to Euston with its new terminus station. Works are underway on this portion but the commentary on schedule was related to the section outside London, to be initially opened, in the plans. What is the impact on costs? The last baseline (B.7.1)


put the cost at £42.9 bn (Q3, 2019 prices), excluding the cost of Euston station (£44.6bn, when included). In the years since the costs have “regularly” increased, but weren’t firmed and still aren’t; there isn’t certainty “that all cost pressures have been identified.’ Stabilisation of costs needs, first, a firmer foundation of the schedule, from a “full programme reset”, the letter says. Digging deeper, three “primary issues” were noted for


the time and cost problems, and all of them were macro choices, made early on: in planning and procurement; and, in programme management. On planning and procurement, the conclusion is the


build started too soon, without enough design done; over optimistic cost and schedule estimates, and not enough provision for risk; efficiencies metrics were not up to the task; the contracting model did not drive performance, and focused on early wins rather than


optimising whole-life, or overall, cost; and, doing so on civils packages that were too big. On programme management, it says the client was


“not set up to actively manage delivery”, and that despite a large headcount in HS2 Ltd there is a relative imbalance on its project delivery team’s size versus that of its corporate team - which “has grown excessively”. The project team’s commercial and technical capacities need boosted. Bureaucracy is criticised, and internal culture - and


that a focus on its de facto core mission appears amiss, in that it does not act “like an expert builder of a railway”, or operator, but rather is construction -focused. It appears insufficient as an owner-operator of a transport system with a focus on serving passengers, long-term, and well. For ambitions now and ahead, HS2 Ltd is to change,


being strengthened and reshaped to focus on delivery as an service provider, not a builder. Wild’s letter talks of “systemic failure” emerging from


pile-ups of “vulnerabilities”, compounding over time; although “there is no single root cause” it acknowledges difficulties due to Covid, Brexit and geopolitics affecting inflation, all worsening matters. The project has been underway in not the easiest of


times, and no review is needed to know that to those externalities can be added further woes, causes by political headwinds, tailwinds, and repeated reversals and twisters. Chaos at the top of politics affects large projects, in their governance, schedules and costs. The plan, now, is proposals by year end, a new


schedule by April 2026, and then to better track progress and performance.


STEWART REVIEW MAKES ITS RECOMMENDATIONS


The Government has accepted all recommendations made by James Stewart following his independent review of the governance and assurance of major transport projects, principally focused on HS2, as performed by DfT, the civil service and politicians with responsibilities in the past. Soon after winning the General Election, the Labour Government commissioned Stewart, in October 2024, to get to work. His report was released publicly in June, along with the Government’s response. Principal findings of the Stewart Review tell of historic mishandling of the huge project, lack of ministerial oversight and scrutiny, and inadequate control by the project’s client - the owner-operator company, HS2 Ltd. Also, effective incentives with supply chain were lacking, resulting in, the Government saying, a position that “will collectively cost the taxpayer billions more than planned.” The Stewart Review gave five key recommendations, which are to: bring back the HS2 taskforce for oversight; negotiate incentives to get cost savings for taxpayers; reform but boost the project client; make a decision on the Euston terminus station; and, ensure other DfT projects benefit.


On negotiating incentives, the new client leadership will


be “renegotiating HS2’s large construction contracts” as well as overhauling the “skills and structure” of the entire organisation. The Review says that both HS2 Ltd and DfT, as project Sponsor, were both “underpowered” to handle HS2’s needs.


The blame, in part, is laid on choosing a ‘lean’ client model


for HS2 Ltd. This “proved to be wrong” and was not changed as problems arose, the Review says. It adds that both HS2 Ltd and DfT lacked sufficient resources, and also skills, with sufficient experience of commercial and delivery activities. Interestingly, it is recommended that, in the reset, the new HS2 Programme be given a 5-year funding control period, with flexibility to move budget between years. Stewart says the project “is in a state of flux and uncertainty,” and a “fundamental reset” is needed to get it finished and trains running. Two positives are noted, though: the scope was tightened previously, after Phase 2 and HS2 East were dropped; and, the engagement of Mark Wild as chief executive.


August 2025 | 27


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141