TRANSPORT | RAIL PROJECTS - HS2
CELEBRATING FINISHES HS2 -
The start and completion of a tunnel is always to be celebrated, and recently the HS2 project has enjoyed a flurry
Over recent months, the HS2 project has had
opportunities for a number of celebrations as drives on many of the large-diameter rail tunnels were completed. Those TBM drives took place outside of central London, where more tunnelling is yet to be done. At the edge of London, in the Chilterns and up near
Birmingham, many different tunnel drives were required, and completed, for the twin-tubes of the high speed rail project. Those TBMs on Phase 1 that are finished have been dismantled.
It is rare for so many large TBMs to be active in the
UK, and even moreso outside of London, and also for them to be completing their bores within relatively tight windows. The TBM drives so far and their finishes are briefly
described below. More are to come, in London, with two TBMs on the Euston Tunnel. Works for the latter were enabled by construction of the Atlas Road Logistics Tunnel, which was completed early 2024. The project also includes some cut-and-cover ‘green’ tunnels.
EDGE OF LONDON HS2’s 13.5km-long Northolt Tunnel was nearing completion of boring by mid-year when the fourth, and last, TBM on this section of the project would arrive and finish its journey at the Green Park Way site, in Greenford, west London. The Green Park Way site sits along Northolt Tunnel,
resulting in the tunnelling works on either side. To the west side is a for the twin-tunnels to be arranged in two groups: to the west is the 8km-long, 8.80m-i.d. western section from West Ruislip; and, to the east is the 5.5km-long, 8.10m-i.d. section that runs closer to London, to North Acton. Northolt Tunnel is one of five deep twin-bore tunnels
on HS2’s 225km-long route. It is the second longest tunnel on the project and runs up to 35m below ground at its deepest point. This section of HS2 extends from West Ruislip via North Acton to new Old Oak Common super-hub station. Contractor is Skanska Costain Strabag JV (SCS JV). It is also building the Euston Tunnel, in central London.
Above: Tunnel excavation at Euston, in late 2024 IMAGES COURTESY OF HS2
22 | August 2025
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137 |
Page 138 |
Page 139 |
Page 140 |
Page 141