CASE STUDIES


Gmac Utilities Ltd


new installation Lower Otter Restoration Projects – HDD


Gmac Utilities Ltd overcame difficult ground conditions to install 520m of 500mm rising main to a depth of 48m whilst drilling under a SSSI wetland and river replacing the existing infrastructure, as part of EA scheme to return 68 hectares back to wetland.


The project involved pipe ramming 60m of 1000mm steel casing through dense river terrace gravels to depth of 18m to the sandstone bed rock, before undertaking the horizontal directional drilling. Not only was the pipe ramming and hdd completed on time and within budget with no environmental impact to surrounding area, the hdd crew performance, site set up and work ethic received praise from some very knowledgeable local residents.


The picturesque seaside town of Budleigh Salterton in Devon was the location for the Lower Otter project, which involved reclaiming past intertidal marshland area, replacement of storm water outfall and a new pedestrian foot bridge. The Lower Otter SSSI area designation was made for both ecological and environmental reasons. The marshland designated area is important for water birds, which rely on


28 | September 2023 | www.draintraderltd.com


the collective ecosystems of plants and invertebrates within that habitat. The geological designated area is the cliffs of Otterton Point ( hdd exit site) which are of palaeontological importance. One significant issue however was that overtime, the top of the existing storm water outfall had become exposed in the bottom of the river estuary, so relining was not an option. Discussion with Gmac Utilities Ltd, water authority, consultants and the Tier 1 construction company led to the need to replace the existing rising main using HDD.


Whilst the exit side ground conditions


were hard sandstone, from entry side to a depth of 18m were dense river terrace gravels. Gmac utilised the Goliath Grundoram from Tracto UK Ltd and in a 2-week programme before Xmas 2022, installed 60m of 1000mm diameter ( 12mm w/t) in 12m sections ( one of the largest pipe rams to date in UK) The lead face of the front casing was prepared with a strengthening band a cutting teeth. The rammer was connected to 2 no 850 cfm compressors and installing time per 10m took between 1 and 2 hours. The pup section with rammer attached was gas cut from the casing and


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76