At the HDD operational sites constructing the crossings of the Deben Estuary and the Martlesham Creek onsite visual barriers will be erected around the works area.


At the Deben Estuary HDD crossing site all construction workers will be given strict instructions not to leave the HDD site and walk up on to the sea wall.


1.6 Mitigation at the Pre-construction Stage 1.6.1 Pre-construction Surveys


26. Pre-construction surveys will be targeted at Schedule 1 breeding species, rather than SPA non-breeding species, due to the need to assess the regularity of nesting at previously identified locations and the potential for such Schedule 1 species to choose new nesting locations.


27. Pre-construction surveys for Schedule 1 breeding species will be undertaken and have the aim of identifying and confirming areas where nesting is regular and mitigation by habitat management might be necessary. Wetland habitats along the cable route that are potential nesting habitats for Marsh Harrier and Cetti’s Warbler will be surveyed using appropriate methods. Survey methods will also be used that will identify the potential for nesting Hobby Falco subbuteo and Barn Owl Tyto alba (both Schedule 1 species that nest at low density in farmland) along and adjacent to the cable route. Survey methods will include an inspection of Barn Owl boxes (using a suitably licenced ornithologist if during the breeding season) within 100m of the route (no boxes are currently known to be used by this species).


28. The SPA non-breeding species have, in the case of Avocet and roosting Brent Goose, habitat requirements that mean their use of the area will not change from year to year and in the case of Brent Goose feeding areas their use of agricultural land will follow cropping practice that changes every year. As a result there is no benefit to be gained from pre-construction surveys for SPA non-breeding species (but note there will be surveys carried out for Brent Goose during the construction phase that will be overseen or delivered by the ECoW).


1.6.2 Targeted Habitat Management Brent Goose


29. No targeted habitat management is proposed for Brent Goose at the pre-construction phase as there is no reason or requirement to carry out any such works in advance of construction.


EcMP: Deben Estuary SPA & Schedule 1 Birds


Page 6


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129