32 PROJECT REPORT
CONSTRUCTION CONSTRAINTS One of the reasons such a linear development, building on a single side of an existing through road, is unusual for Cameron Homes, are the challenges it places for the construction process itself, including for planned movements and traffic movements. e basically created a haulage road at the front of the site,” says Paul, “and tried to access everything from within the site until we got down to the last few plots, where we worked off the side of the road effectively. ust-in- time materials management was needed, which, says Paul, so that the team only had material on site when they needed it. However this in itself was particularly difficult given that the scheme took place “at the tail end of Covid.” He laughs: “I remember my
construction manager at the time looking at it and saying ‘thanks’!” Paul says that while there weren’t any major S278 highways works on this project, they had to create 20 dropped kerbs, “so we ended up reconstructing all of the footpath and the drainage in the carriageway.” There had previously been localised flooding, and the ighways Authority asked the developers to improve and repair drainage as part of the project, which added extra time, as well as making the normal foul and stormwater connections to the mains for the new homes.
The demolition process was involved,
WWW.HBDONLINE.CO.UK
partly because the team had to work at night, and weren’t allowed to begin until .am on the final hoppers and towers remaining on the site. Permissions were required from Network Rail, because the demolition staff were working at height adjacent to the track, albeit when trains weren’t running, and that was a “challenge in itself,” says Morrissey. Local residents enjoyed this nighttime spectacle: “Some were sitting out on the footpath with deckchairs and flasks, and there was a big cheer when the tower finally came down he whole process only took four hours using specialist machinery, and the team returned to cut up and remove the demolished structures the following week. t’s the first time in my career I’ve done that overnight,” says Morrissey.
Along with the buildings, there were a lot of “unkept and unmanaged” Poplar trees along the railway that needed “some substantial work,” and thereby entailed further co-operation with etwork ail including them taking a ‘watching brief’ over the developer’s work. Some of the trees were removed during the overnight demolition to maximise the potential of the machinery and manpower at that stage. “It was busy for four hours!” says Morrissey.
There was hydrocarbon contamination in the ground from decades of cement lorries leaking oil, and this was a challenge to address, preventing it
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100