SPECIALIST EQUIPMENT
MOBILISING MACHINES Mining equipment transportation intelligently engineered in South Africa A
round 75% of South Africa’s energy needs directly rely upon coal mining. So, when a new site is opened, it’s vital that key equipment is mobilised as quickly and efficiently as possible; both on a local and national level. Such was the case when a face shovel
excavator needed transportation from Kromdraai Colliery in Mpumalanga Province to a new cut in nearby Emalahleni. ALE was able to mobilise at short notice and provide equipment well- suited to a fragile road surface and critical bridge structures. ALE received the 552t Terex O&K RH340 face shovel machine from the client at a designated spot on site. A tracked vehicle, it is capable of crawling between different cuts on site by itself. It is, however, not capable of crawling any great distances between sites or on public roads. So, it was necessary to split the machine into two primary pieces for transportation: the 291.5t main machine and the 207.9t undercarriage. ALE preferred a four- point lifting system methodology for the splitting procedure, which offered increased stability over crane-based approaches and was less susceptible to sourcing issues. It was the first time the
Te trailer – attached to two prime
movers at the front of the trailer and one to the rear each with 28t ballast – set off along its 25.4km route. Besides ground pressure, the route had been analysed in advance to make sure its vertical radii didn’t exceed the navigable parameters of the 77.1m long convoy.
Arrangements had also been made in Loading the machine onto the trailer
client had attempted to split any of its machines with this methodology. Te main machine and undercarriage
were first decoupled before the former was attached to the four-point lifting system, which was raised to a total height of 8.1m. Tis provided the necessary clearance for the tracks, which were self-propulsive, to be driven out from underneath the suspended main machine. ALE deployed a Goldhofer THP/SL 22-axle trailer for this project. At 37.8m length and 4.3m width with 1.8m axle spacing, it was sizeable, however, smaller trailers would not have been able to cross over the critical bridge structures on the route.
advance with a local steel smelting plant, such that high-voltage power lines could be switched off for a small window of time, allowing the transportation to pass. Te passage was otherwise smooth, as the journey was planned not to pass through built-up areas.
LIFT AND LOAD Upon reaching the Emalahleni site, the main machine was staged off onto four stools lined by two 7m header beams at a height of 1.6m. Te team then returned for the 207.9t undercarriage, which was lifted by the same four-point lifting system to a clearance of 1.63m, then transported using the same equipment configuration. Te face shovel was then reattached
by the client after its undercarriage was manoeuvred underneath the waiting main machine. It is now hard at work on site, operated by one of South Africa’s 90,000-strong coal mining workforce.
ALE was able to provide equipment at short notice
36
www.engineerlive.com
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56