search.noResults

search.searching

dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
32 PROJECT REPORT: HERITAGE & CONSERVATION


Interior images ©Sara Reynard Photography


building’s “massive, deep foundations” were amply capable of supporting the “fairly small and lightweight” new build element. As such, the team managed the project without piling, just using traditional insitu poured concrete.


He describes how the existing brick frame starts off very thick at the bottom, and gradually gets thinner toward the upper stories. Structures were typically constructed this way in the pre-steel era, masonry and cast iron columns having to take the vast bulk of the buildings’ loads. The existing brickwork of the Mill was “in pretty good condition,” the architect tells ADF, and as such there weren’t many necessary remedial works – only “a few bits” of pointing and repairs to sills. When it came to the added brickwork elements in the new wing, however – which were also constructed as load-bearing masonry with concrete planks to fit with the existing structure – Cooper says it took some “fairly lengthy” technical analysis to achieve LABC accreditation.


Roof


Moving up to the roof extension, sitting above both the new build and restored sections, the team turned to Fusion Building Systems to create a structure lightweight enough to be supported by the brickwork. Cooper explains that these additions were necessary to meet the client’s brief for an increased number of homes in the


WWW.ARCHITECTSDATAFILE.CO.UK


project’s footprint. The retained chimney previously stood alone together with “a kind of boiler house,” so the architects enacted the wing extension through this new linking block that wraps around it, and which subsequently “leads it all back to the mill.” Then, in order to achieve the two new floors added above all this, the team had to remove the pitched slate roof from the existing brick portion, as well as undertake the removal of some “insensitive additions and links” made in the past during the building’s conversion to office space. “The developer did a really good job of sourcing all these materials to recreate the key details,” the architect adds.


Structural stress


When it came to structural challenges around adding the new floors above the existing building, “there was a lot of technical work necessary to get it right,” Cooper explains. A bespoke, “highly complex” metal grill system was used to connect the base of the new floors to the existing building and fully support the ‘fusion frame’ system at the point of transition.


The team was surprised to find that in stripping out the existing brickwork structure, it was out of level by around 300 mm across the length of the building. “Nothing’s square when you’re dealing with these old buildings,” says Cooper.


ADF JANUARY 2021


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76