[OFFICES] George Howard Building | Ellicott City, Md.


›› Retrofit Team ARCHITECT: Polleo Group, Reston, Va., polleogroup.com BUILDING-MATERIALS DEALER: Parkway Associates Inc., Rockville, Md., (301) 770-2675 GENERAL CONTRACTOR: Clark Construction Group LLC, Bethesda, Md., www.clarkconstruction.com INSTALLER: Phillips Fabrica- tors, Rockville, (301) 881-3129


›› Materials


The following metal wall panels, which feature moisture-resistance and thermal qualities, were used on the facility:  Formawall Dimension Series 3-inch Horizontal: 10,533 square feet in champagne gold with a Sundance AM coating and embossed finished, 22 gauge


 Profile Series Concept Series CS-660: 1,577 square feet in champagne gold with a Sundance AM coating and embossed finished, 22 gauge


Manufacturer: Centria, www.centriaperformance.com


›› The Retrofit The 98,500-square-foot George Howard Building first opened to the public in 1978 and is home to the administrative offices for the Howard County, Md., government executive branch. The build- ing also houses offices focusing on everything from general public information to tourism. After 32 years, the building was in dire need of modernization, which led to a $23.5 million renovation. In addition to reconfiguring the building to make it easier for visitors and employees to navigate, sustainability was a core goal of the project. Nearly every piece of the four-level building was re- moved and replaced with a new energy-efficient alternative. Notable sustainability initiatives include a redesigned metal exterior, an underground rain cistern, solar panels on the roof and solar-powered street lights, a parking lot with reserved spaces for hybrid or electric vehicles, motion sensors to con- trol indoor lighting and new light fixtures that are expected to save about 20 percent on energy.


Arden Realty | Irvine, Calif. Shelburne Green | Shelburn


›› Retrofit Team ARCHITECT: J. Graham Goldsmith Archi- tects, Burlington, Vt., www.jggarchitects.com GENERAL CONTRACTOR: DHCameron Construction Co., N. Ferrisburgh, Vt., (802) 425-3782


›› Materials


A total of 36,000 square feet of insulated metal panels in the following profiles were utilized on the project:  Light Mesa in Polar white and silver, installed vertically


 CF Fluted in Polar white, silver and zactique, installed horizontally


 7.2 Insul-Rib in bright red, installed vertically Manufacturer: Metl-Span, www.metlspan.com


›› Retrofit Team ARCHITECT: Spaces Planning & Design, Irvine, www.spaces-oc.com LIGHT-GAUGE FRAMING DESIGNER: Architectural Systems Inc., Poway, Calif., www.asi-sd.com PANEL INSTALLER: Emerald Metal Products, Signal Hill, Calif., emeraldmetalproducts.com


›› Materials More than 36,000 square feet of Envelope 2000 metal composite material was used on the project. The panels were finished in clear anodized and Shasta white and installed using the Reveal System, a field-assembled attachment method utilizing perimeter moldings.


Manufacturer: Citadel, www.citadelap.com ›› The Retrofit


The building was originally constructed in the early 1970s and featured a rough-finished stucco. “The biggest challenge was with the existing building being out of square and out of plumb. The conditions were definitely not good,” explains Dale Gronewold, owner of Emerald Metal Products. Gronewold’s team built a 16-gauge framing structure in 40-foot sections on the roof and lowered it to the ground. Then, the metal panels were attached to it.


32 RETROFIT // November-December 2012


PHOTO: CITADEL


PHOTO: CENTRIA


PHOTO: METL-SPAN

Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68