This page contains a Flash digital edition of a book.
thought it would be relatively easy to get plan- ning permission to build a farmhouse for them- selves and their three sons. Instead it took five long years of patient nego-


W


tiating, perserverence and optimism to get the go-ahead for a four-bedroom family home, and a further two to reach the point where they could finally move in. “It was a very drawn-out process,” says


Simon. “There were changes to the family busi- ness arrangements which gave us the opportu- nity to buy the land and expand the farm.” They were also living in a two bedroom


cottage and needed more room as the boys got older. They ploughed everything they had into the land and farm buildings, on the outskirts of Pocklington, and applied for planning permis- sion to build a farmhouse on site so they could run the business as efficiently as possible. But their application was turned down on the


basis that there was no functional need for a family home. “They wanted to see three years of business accounts and for us to prove a functional and financial need for a house on the site,” says Simon. “It didn’t make sense to us – we already had a small cattle herd and a poultry business and saw this as an expansion of the existing business.” Undeterred, Fran and Simon managed to get


permission to create temporary accommodation in the form of pre-fab cabins, so they could still live on site while running the farm and collating the documents required to re-submit their plan- ning application. “We put in for a larger house than we actu-


ally wanted, fully expecting it to be knocked back,” says Simon. “We were delighted when East Riding of Yorkshire Council finally granted planning permission, without change to its size, on October 13 2013 – the date is permanently etched in my mind!” “Until this point Simon had refused to plan


anything at all to do with the build in case it was rejected again,” says Fran. “The whole process was really draining. Then suddenly it was all systems go and we could start to look ahead.”


Continued overleaf... [


It took five long years of patient negotiating, perserverence and optimism to get the go-ahead for a four-bedroom family home


hen Fran and Simon Ackerley bought 200 acres of prime East Yorkshire farm land in 2008 they


THE HIGH GLASS WINDOWS IN THE HALLWAY FILL THE PROPERTY WITH NATURAL LIGHT


]


THE FOUR BEDROOM HOUSE IS A MIX OF TRADITIONAL AND MODERN DESIGNS AND FURNITURE


selfbuilder & homemaker www.sbhonline.co.uk


23


LOW POINT


We laid water based underfloor heating topped with screed, which


took six weeks to dry, and were ready to lay the tiles when we were told the underfloor heating needed to have been


running for a week beforehand. We didn’t have a boiler at that point, so everything was put on hold while we got it installed and the underfloor heating on by the end of November. That gave just


enough time for the tiles to be laid and kitchen units installed before Christmas


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76