This page contains a Flash digital edition of a book.
FEATURE SPONSOR


ROVS CASE STUDY TOOLKIT


The culmination of this ongoing development that has spanned 15 years is UTROV`s Generation 4 System. This tool kit includes a MFE, clamshell bucket, tined grab, shear grab, timber grab, sampling grab and mattress laying frame; all of which can be changed out on deck quickly to ensure the UTROV can handle a range of tasks.


The UTROV provides a subsea platform and means to operate and control hydraulic systems, existing tooling from the construction industry can be easily adapted to work subsea or new tooling can be developed to carry out specific tasks.


Late in 2014 UTROV were employed by Briggs Marine to provide subsea support for the recovery of a 29t tool that was partially buried in 105 metres of water. Approximately 110 meters of tow wire and umbilical were still attached to the tool potentially hindering ROV operations.


The remit was to dredge around the tool, lift it clear of the sea bed and move it to a site approximately 3 miles away with a water depth of 20 metres. Here it would be positioned on the sea bed for Briggs divers to replace the lifting harness prior to recovery.


THE KEY OPERATIONAL STAGES WERE IDENTIFIED AS… • Survey • Possible removal of tow wire & umbilical obstructing access


• Excavation around the tool • Attaching a hoist wire • Lift the tool clear of sea bed • Move the tool to a pre-identified site • Lower and uncouple the tool


THE CONVENTIONAL APPROACH Use a combination of an ROV and a MFE to carry out the operation. The vessel used would have needed sufficient deck space for the 2 systems, berths for the operators and a winch or crane to support the operation.


THE UTROV APPROACH The adaptability of the UTROV made it possible to quickly engineer solutions for the various problems associated with the project…


1 A timber grab was purchased and modified to interface with the UTROV. This was fitted whilst carrying out the survey of the tool to allow the immediate removal of the tow wire and umbilical


2 On completion of the survey the MFE was attached and deployed. Two acoustic cameras were fitted onto the UTROV allowing the operator to closely monitor the excavation site at all times


3 A two wire grab was designed for latching onto the stranded tool and lifting it without damaging it. This was designed, manufactured, tested and delivered in 10 days. Key factors in the design of the two wire grab were that it would grip hold of the tool without causing damage and that it would be able to release the grab from the tool should the need arise due to deteriorating weather


4 The two wire grab (weighing 2.5t) was suspended in the open position from the UTROV using the timber grab to hold a buoyant spreader bar (See inset picture). Once in position the timber grab was released transferring the load onto the main winch wire of the vessel. An additional buoy provided a constant tension on the winch wire preventing the grab from being unintentionally released with the vessel movement in the swell


5 The UTROV was recovered to the surface and the tool was successfully lifted and repositioned using the vessels main winch. The UTROV was deployed again to grip the spreader bar releasing it from the tool


A SUCCESSFUL AND COST EFFECTIVE SOLUTION


This was a successful operation all carried out from Briggs Marine’s capable 61.2m x 13.5m vessel with a crew of 11 and a 4 man UTROV team providing a cost effective solution to the client.


Utility ROV Services Click to view more info


www.windenergynetwork.co.uk


55


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100