This page contains a Flash digital edition of a book.
FEATURE SPONSOR


LEGAL EAGLES


VARIATIONS IN PROJECT SCOPE Construction risk includes variations or changes in project scope include…


• Force majeure • Weather • Delay • Ground or sub-surface conditions • Contractor and design team experience


• Solvency • Familiarity with local conditions and requirements


The incidence and effects of these areas will need to be dealt with in any contract.


LEGISLATION & REGULATION Legislative and regulatory risks will also impact on the project risk profile and can expose owners to delays, fines or additional costs of delay if licences or permits are not available on time. Such risks are generally not insurable and fall to be taken by the owner.


TECHNOLOGY


Construction contracts, whether on or offshore, are simply a vehicle to determine how risk is to be shared between the parties and to consider issues such as risk transfer and risk mitigation.


The areas to be considered include…


• Construction • Environmental • Regulatory • Technological • Operational


SELECTION


The choice of the procurement route is fundamental, as is the contract form, with many renewable energy projects adopting one of the several FIDIC contract forms - the specific form being dependent on the type of project.


The various areas of risk themselves can be subdivided.


The ability to attend to failures, whether from defects in manufacture or construction, or the ability to maintain and service machinery and equipment of projects, is highly compromised due to the location of the asset, accessibility and factors including the weather and quality of service personnel.


OPERATION


In operational terms the asset, once constructed and commissioned, needs to operate with a high degree of reliability and minimal maintenance. Increasingly equipment is being developed to minimise the need for high levels of maintenance visits.


As a result of this, should a failure be found there is a tendency to replace all units to avoid future problems – a stitch in time approach.


Technological risks, which are linked to operations and maintenance work, are high in renewable energy projects because the equipment and machinery is required to perform to a high level of efficiency over a long period of time.


PROJECT DELIVERY


All these areas impact on a project’s ability to deliver power and income and also to secure finance packages.


The correct approach to these risks will assist in the attitudes of investors towards the project.


BALANCE


A careful balance however needs to be struck between the respective parties to determine the party best able to bear the risk.


Martin Collingwood Associate


Andrew Jackson Solicitors Click to view more info


www.windenergynetwork.co.uk


45


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116