Flood Defence 60 Flood Alleviation Schemes announced for 2013 60 Schemes
25,000 Properties better protected £2.17Bn of Government Investment £72M Partnership Funding
As well as the 60 new schemes, 80 schemes still in progress will still continue to receieve funding
Over 25,000 more homes will be better protected from the effects of flooding by new defence schemes to start construction in the next financial year, Defra and the Environment Agency have confirmed today.
In total, 60 flood and coastal risk schemes will begin construction this year. Those given the go ahead today include Warrington in Cheshire, protecting over 1900 households, Salmons Brook in North London, protecting over 1300 households, and Godmanchester in Cambridgeshire, protecting over 300 households.
Exceeding targets
New estimates also show that the Environment Agency is now on track to exceed its target of better protecting 145,000 homes by 2015. Thanks to the new partnership funding approach, which encourages funding from external sources such as councils and businesses, over £72million of contributions have been secured to help fund flood and coastal erosion schemes on top of the £2.17 billion Defra is investing in preventing flooding during this spending period to 2015.
Regional Flood and Coastal Committees have worked with local communities to attract flood defence funding from sources such as councils, businesses and private investors. This Partnership Funding approach was introduced in May 2011 to encourage
New flood defence construction starts in England in 2012/13 Total Project Name RFCC Risk Management Authority
Scheme Cost £m
River Mersey Warrington FRM Scheme Morpeth Flood Alleviation Scheme Sandwich Town Tidal Defences Steart Managed Realignment
Salmons Brook Flood Alleviation Scheme
River Tame, Whitacher, Tamworth and Fazeley, Coton,Flood Alleviation Scheme Littlehampton Arun Tidal Defences East Bank Cromer Coast Protection Scheme
Godmanchester Flood Defence Improvement Scheme Chelmsford Flood Alleviation Scheme Deal Sea Defences - Sandwich Bay Greatham North
Hatton, Scropton & Egginton, Lower River Dove, Flood Alleviation Scheme River Irwell, Salford Asset Management Whittlesey Washes Reservoir Works
Portsmouth Hotspot 14 (Flap Valve, Sever Disconnection, Storage) SWMP phase 1 Thames Weirs High Priority Programme Package 2 Seaton Carew Northern Management Unit Phase 2 Leigh East Flood Risk Management Scheme Water End Flood Alleviation Scheme, York Rawcliffe Bridge Embankment Repairs, River Don
Northallerton (Sun and Turker Becks) Flood Alleviation Scheme Mill Beck Reservoir Works, Market Weighton Penton Hook Restoration
Newbury Flood Alleviation Scheme Beverley Brook at Worcester Park Lewsey Park Flood Storage Area West Wittering Flood Banks
Hartlepool Town Wall Model Study & Construction Dartford Security Emergency Works
Leigh Barrier Mechanical Improvements Phase 2
Portsmouth Hotspot 9 - Flap Valve and Storage (SurfaceWater Management Plan) Warnham Mill Reservoir - work to conform to the Reservoirs Act Gilberdyke & Blacktoft Flood Management Project Rolle Quay Flood Defence repair, Barnstaple Upstream Thames Weirs Guard Pile Replace
Severn Estuary, Severn Vale Water Management Plan River Wey Strategy Works (Weirs Phase1) Eastrington & Laxton Flood Management Project
Upper Thurne Water Level Management Plan - Brograve Ochre & Salinity Saddler's Mill Stream Culvert Refurbishment
Scarborough North Bay Urgent Seawall Repair Programme
Lubbesthorpe Brook, Lubbesthorpe, Leicester, Flood Alleviation Scheme Fairford Critical Evaluation Thames Barrier Peir Fenders
Roaring Gutter Island bank stabilisation Colchester East Mills Sluice Tilbury East Dock Channel
Theobalds Flood Storage Area Embankment Repairs Jack's Key Reservoir Interim Safety Works Bridge Road Emsworth, Flood Alleviation Works Kirkley Stream
Mill Avon, Tewkesbury, Abbey Mill Fishbelly Sluice, Gate Inspection & Stop logs Cranleigh Watercourses
Plymouth, The Plym, Arnolds Point,sea wall reconstruction Hirst Marsh Pumping Station
Portsmouth Hotspot 6 - Storage (SWMP Phase 1) Hobhole Sluice Door
Skidby Appraisal and Construction Kerridge Pumping Station Improvement Works
Total number of new schemes entering construction: Total number of environmental schemes
Total number of Health & Safety / legal schemes Total number of households protected by new starts:
Total value of contributions (inc. local levy) for schemes starting in 2012/13 (£m)
North West Northumbria Southern Wessex Thames Midlands Southern
Anglian Eastern Anglian Central
Northumbria Midlands
North West
Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency
North Norfolk District Council Environment Agency
Anglian Eastern Environment Agency Southern
Environment Agency Environment Agency Environment Agency Environment Agency
Anglian Northern Environment Agency Southern Thames
Northumbria North West Yorkshire Yorkshire Yorkshire Yorkshire Thames Thames Thames Thames Southern
Northumbria Thames Southern Southern Southern Yorkshire
South West Thames Midlands Thames Yorkshire
Portsmouth City Council Environment Agency
Hartlepool Borough Council Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency Environment Agency
Hartlepool Borough Council Environment Agency Environment Agency Portsmouth City Council Environment Agency
Lower Ouse Internal Drainage Board Environment Agency Environment Agency Environment Agency Environment Agency
Lower Ouse Internal Drainage Board
Anglian Eastern Broads (2006) IDB Thames Yorkshire Midlands Thames Thames Southern
Environment Agency
Scarborough Borough Council Environment Agency Environment Agency Environment Agency Environment Agency
Anglian Eastern Environment Agency Anglian Eastern Environment Agency Thames
North West Southern
Environment Agency Environment Agency Environment Agency
Anglian Eastern Environment Agency Midlands Thames
South West Yorkshire Southern
Environment Agency Environment Agency Plymouth city council
Selby Area Internal Drainage Board Portsmouth City Council
Anglian Northern Witham 4th District IDB Yorkshire
60 5 9
24,814 53.0
East Riding of Yorkshire Council Anglian Central Padnal and Waterden IDB
18.4 13.7
28.9 21.0 19.9 19.9 !8.4
11.3 10.2 8.8 8.6 8.1 7.2 7.1 6.7 5.2 0.3 4.3 4.1 3.6 3.4 3.3 3.2 3.2 3.0 2.5 2.2 1.9 1.7 1.6 1.5 1.5 0.7 1.4 1.2 1.2 0.9 0.9 0.9 0.8 0.8 0.8 0.7 0.7 0.7 0.6 0.3 0.5 0.5 0.4 0.4 0.3 0.4 0.4 0.3 0.3 0.3 0.3 0.3 0.3 0.3
In addition, aro through the co
external contributions so that taxpayers’ money is spread across more schemes.
The Partnership Funding model targets areas of severe flood and coastal erosion risk, and homes in deprived communities. Of the 145,000 homes that will be better protected by 2015, around half are in areas of significant flood risk and almost 15,000 households are both at significant flood risk and in the most deprived parts of the country. Partnership Funding gives local people greater choice about what flood protection is provided in their area.
In Cockermouth, £3.3 million funding from Defra makes up part of the funding to enable a flood scheme to be built in the town, which the local community and local councils have also committed to help fund.
A scheme in Water End, York, which was turned down for funding last year, is going ahead after the Environment Agency worked with York City Council to agree a package of cost reductions and partnership contributions.
As well as the flood schemes that will progress as result of this year’s funding, the allocation for 2012/13 also covers maintenance of existing defences. The Environment Agency has also committed to increasing the number of people receiving free flood warnings to over 1.1 million.
For all your Land Drainage Requirements
Land Drainage
Cross Country Pipelines
Utility Installation & Trenching Works
• • • • • • •
Other Drainage Works
As well as Agricultural Land Drainage we also specialise in: Irrigation & Water Services Culverts Ditching Works & Watercourse Maintenance Land and Pond Construction Sports Fields and Recreational Areas Caravan Sites (Existing & New Build) Golf Courses / Driving Ranges
E.mail:
sales@dmjdrainage.co.uk • Tel: 01205 480 958 • Fax:01205 480 977 DMJ Dranage Ltd, The Offices Medlam Lane, Carrington, Boston, Lincolnshire, PE22 7LU
www.dmjdrainage.co.uk 12
www.fadsdirectory.com
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38