This page contains a Flash digital edition of a book.
DATA CENTRES EVAPORATIVE COOLING


Hot dry air


Figure 1: This diagram shows the principle of evaporative cooling – latent heat is removed from the hot dry air as a result of the evaporation process of the water circulating in the system, which in turn results in a cool air output


Cool air


decided to look at installing a form of ‘free cooling’ to the data centre room. After investigating a number of alternatives, it was felt that an evaporative cooling system would be the most suitable form of cooling for the data centre’s requirements, as this solution appeared to be able to maintain a relatively stable internal environment in terms of temperature and humidity, regardless of the external conditions. In order to achieve the required 150 kW


Owing to the success of this project, Nottingham Trent University is currently investigating a number of other locations where this type of system could possibly be installed


cooling requirements of the data centre, five evaporative cooling cubes were needed, each with an equivalent cooling capacity of 35 kW and a COP of 2.4. The principle behind the cooling solution


is shown in Figure 1: heat is removed from the hot, dry air as a result of the evaporation process of the water circulating in the system, which in turn results in a cool air output. The evaporative cooling system proposed for the data centre also had the potential to benefit from free cooling during periods of the year when the external dry-bulb temperature was below that of the required internal temperature. With a target internal temperature of


24C, and a constant load throughout the year, it was estimated that the electricity requirements of the system would be 22,847 kWh, as the evaporative cooling


46 CIBSE Journal October 2011


system would benefit from free cooling during the winter, and would be able to regulate the required energy input into the system according to the external temperature and humidity levels. Compared with the energy requirements


of the cooling system it was to replace, the forecast energy saving that could be achieved by the evaporative cooling system was up to 89%.


Payback Taking into account the energy savings of the proposed new system, the financial savings at current energy prices were estimated to be more than £16,500 a year. The project cost, installing all of the required equipment and controls, was quoted at just under £72,000 and, as such, provided a simple payback of less than 4.4 years. This simple payback does not include the maintenance required for the new system, but this was more than offset by the maintenance costs that would have been needed for the cooling system that was being replaced. In addition, the costs associated with


water requirements were not taken into account in the above payback calculations. These were anticipated to be extremely low, as at their peak load each unit would


www.cibsejournal.com


Water circulation


EcoCooling/Celsius Design Ltd


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80