This page contains a Flash digital edition of a book.
DATA CENTRES EVAPORATIVE COOLING


W


hen it came to further enhancing the data resilience and security of Nottingham Trent


University’s computing network, it was identified that the storage requirements of the network based at the university’s Clifton Campus data centre needed to be improved. To facilitate the required network upgrades, however, it was also deemed necessary to carry out a number of improvements to the data centre and its supporting infrastructure. Prior to the refurbishment works, the


required cooling for the data centre room was provided using a 150 kW split system containing R407c refrigerant. As a result of planned works, engineers noted that it would be the ideal time to address the cooling system in the room, in order to assist in meeting Nottingham Trent University’s carbon reduction target of 48% by 2020, based on a 2005 baseline. As the cooling equipment in the


data centre was not sub-metered, it was necessary to estimate the energy used by the system, so that the team could look at possible options for cooling in the data centre, and, as such, the subsequent energy and carbon savings that could be achieved. The university employed a heating and


ventilation sub-contractor to assess the efficiency of the current cooling system and to estimate the energy consumption of the units over a period of a year. It was estimated that, due to the age of the system and the refrigerant used, the coefficient of performance (COP) of the system would be about 2.75. In order not to overestimate the energy consumption of the current system, and subsequently overestimate any potential savings, it was assumed that the system would operate at 50% of its potential output throughout the year, despite the fact that there was known to be a constant cooling requirement in the room


www.cibsejournal.com


of between 100 kW and 150 kW. From this, the annual energy consumption of the current system was estimated to be around 238,909 kWh. At the same time as the proposed upgrade works to the system were being assessed, the university was also in the process of installing a new cast resin transformer in order to reduce the onsite voltage and benefit from the energy savings associated with minimising overvoltage. This installation was forecast to reduce energy consumption by 8.19% and, to ensure continuity with all of the calculations, this potential saving was also taken into account when estimating the annual energy consumption of the current cooling system. Applying this additional 8.19% energy saving reduced the estimated total annual consumption of the current system to 219,342k Wh. With an annual energy consumption


base established, it was possible to assess the possible options available for the cooling of the room.


Free cooling First, the possibility of reducing the cooling requirements of the room was considered. However, because of the upgrades and additional IT equipment to be installed in the data centre, this was not possible. Second, the option of fitting more energy efficient air conditioning was looked into, but nothing could be found that would achieve the required degree of energy saving. Having considered these options, it was


October 2011 CIBSE Journal 45


The data centre’s new cooling system was estimated to be able to deliver energy savings of 89%


Taking into account the energy savings of the proposed new system, the project provided a simple payback time of less than 4.4 years


Scott Brooks


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80