USA offshore
CAPE COD BAY
CAPE COD New Bedford
BUZZARDS BAY
Covell’s Beach
switching station (115 kV)
Barnstable Vineyard Haven
MARTHA’S VINEYARD
NANTUCKET SOUND
After achieving all necessary permits, among them approval from the US Bureau of Ocean Energy Management (BOEM) and culminating in final authorisation from the Federal Energy Regulatory Commission (FERC), Vineyard Wind executed an agreement with ISO New England to connect its generation into the New England electric power grid – at the NSTAR 115kV switch station in Barnstable, Massachusetts – and signed long-term energy sale agreements with Massachusetts electricity distribution companies.
ATLANTIC OCEAN
MAP KEY
Operation & maintenance Construction port Offshore substation
Existing substation Existing submarine cables Vineyard Wind cable corridor Horizontal directional drilling (HDD)
NANTUCKET
Offshore substation
Vineyard Wind 1 Lease area OCS-1 0501
In October 2023, Avangrid and CIP announced that Vineyard Wind I had closed a $1.2 billion first-of-its-kind tax equity package for commercial-scale offshore wind with three US-based banks. Windar Renovables has been responsible for manufacturing the project’s 62 wind turbine foundations at its plant in Asturias (Spain), a contract worth around 100 million euros.
South Fork Wind’s turbines were staged and assembled at State Pier in New London, Connecticut. The project’s foundation components were completed at Ørsted and Eversource’s fabrication hub at ProvPort, in Rhode Island. Crew vessels and the crew change helicopter was based in Quonset Point, Rhode Island. The project includes the first US-built offshore wind substation.
Long Island based contractor Haugland Energy Group LLC installed the underground duct bank system for the onshore transmission line and led the construction of the project’s onshore interconnection. LS Cable installed and jointed the onshore cables with support from Long Island’s Elecnor Hawkeye. Roman Stone, also on Long Island, manufactured concrete mattresses to protect the undersea cables, and Ljungstrom, located in western New York, in partnership with Riggs Distler & Company, provided specialised structural steelwork.
Meanwhile, progress is being made towards bringing the USA’s first large scale offshore wind facility, the 806 MW Vineyard Wind I farm, fully into operation, which is considered achievable by end 2024/early 2025. It will employ 62 GE
World Wind Technology
Vernova Haliade-X wind turbines rated at 13 MW each.
A 50/50 joint venture of Avangrid (member of the Iberdrola Group) and Copenhagen Infrastructure Partners (CIP), first power from Vineyard Wind I, which is located off the coast of Massachusetts –15 miles south of Martha’s Vineyard and 34 miles south of the Cape Cod peninsula – was delivered to the grid in January 2024. Once commercial operation is achieved, Iberdrola will assume responsibility for operation and management of the wind farm under an agreement reached with CIP. Vineyard Wind I has been supported by a $3 billion investment guaranteed through contracts with three key energy providers.
Construction began on Vineyard Wind I in November 2021, the project having reached a $2.3 billion financing agreement with nine global lending banks, the first financial close for a commercial scale offshore wind project in the USA. The financing included a long-term power purchase agreement and an electricity interconnection programme, and allowed construction to begin, with the aim of starting to supply clean electricity to Massachusetts in 2023.
Prysmian Group, after entering into an agreement worth 200 million euros, was responsible for the submarine cabling system connecting the offshore wind farm with the continental US power transmission grid. The project required a total of 134 km of high voltage AC cable. US company Southwire was in charge of the design, manufacture and installation of the more than 51 kilometres of high voltage overland cable.
In July 2023, installation of the offshore substation that will serve the entire Vineyard Wind I project was completed, the first of its kind installed by Iberdrola in the USA. ●
South Fork blade load out (photo: Ørsted) 33
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41