SHAFTS & CAVERNS | TECHNICAL


INCLINED BORE FOR HYDRO TBM


Pingjiang hydropower project, in China, recently saw a CRCHI TBM complete bored inclined tunnelling for a diversion shaft.


A variable diameter TBM manufactured by China Railway Construction Heavy Industry Co (CRCHI) recently completed its drive to finish boring on an inclined shaft for Pingjiang hydropower project, in China. The shaft, bored at an inclination of 50°, CRCHI says,


and is for part of the flow diversion among conveyance tunnels at the underground pumped storage project. The successful excavation completed the first diversion inclined shaft for the project, achieving finish in June. Tunnel boring was performed by a large, variable


diameter TBM from CRCHI. For the inclined boring, the TBM - named ‘Tianyue’ - had its excavation diameter adjusted from 6.5m to 8m, says the manufacturer. CRCHI says the shield is a first in large-inclination,


large-diameter, and adjustable diameter TBMs for hard rock tunnel boring on sloping shafts. The TBM drive up No.1 diversion inclined shaft was


almost 1338m in length. For the inclined drive, the TBM (87m long, 900 tonnes)


was equipped with a triple-gripping hydraulic interlock system, says CRCHI. Three sets of grippers anchored to the shaft wall formed an “anti-slip triangular matrix”.


During boring, the mid and rear grippers provided counter-thrust while alternating re-gripping every 1.5m, it adds. The hydraulic design of the inclined shaft - and


consequent increased tunnel excavation challenge - arose in part from seeking lower water flow velocities at one end when the power plant is in operation. With flow rate reduced the risk of cavitation bubbles being generated was designed out. At the other end of the shaft the design reduced the


steel use by almost a third to handle high hydraulic pressures during the life of the plant. The TBM tunnelling solution for the inclined, variable


diameter shaft also reduced construction risks for such a large excavation. CRCHI says that, in designing the TBM, consideration


was given to both the excavation capabilities and structural design for two large span openings of different diameters. The TBM design for adjustable diameter can use a single set of equipment, which helps to reduce costs - which the manufacturer says is like equipping the machine with an “extendable skeletal structure.”


Above: Variable diameter inclined shaft TBM breaks through on China’s Pingjiang pumped storage hydropower project PHOTO CREDIT: CRCHI


October 2025 | 11


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45