NEWS |
Auckland trenchless dig TBM completes outfall drive
São Paulo revised
procurement plan for immersed tube bids BRAZIL - São Paulo’s state government has revised its concession plan and republished its bids call for the Santos–Guarujá immersed tube, the country’s first such tunnel. The revised procurement notice includes
technical and operational adjustments to the 30-year concession model, aiming to increase the appeal to the private sector, give greater legal certainty, and to enhance efficiency of the contract execution. The 1.5km-long tunnel for light rail,
Above: The small diameter TBM arrives at Onehunga Wharf in Auckland after completing its bore for a treated effluent outfall off Clarks Beach, as a key step in the project to improve water quality in the Manukau Harbour PHOTO CREDIT: WATERCARE
NEW ZEALAND - The 1.2m-diameter, 19.5-tonne TBM boring for a new wastewater pipeline in Auckland has completed its drive off Clarks Beach and recovered to docked at Onehunga Wharf The outfall for treated effluent
is a key part of Watercare’s investment to improve water quality in the Manukau Harbour. The 240m-long drive took seven
weeks. It holed through to receiving pit 10m under the sea and then two weeks were spent preparing for its recovery to the surface. The TBM had installed a steel
pipeline with a high-density polyethylene (HDPE) carrier pipeline pulled through inside. Divers unbolted the small diameter shield from both the steel and HDPE pipelines, respectively. Lift bags were used to float up
the small diameter TBM to the surface where it was secured to a pontoon barge and taken back to land where it would undergo servicing. The HDPE carrier has been
plugged to prevent leaks or ground and seawater intrusion prior being brought into service. Installation of the full outfall is
expected to the best part of two months. A 66m-long diffuser be installed
at the end of the outfall. The diffuser is designed to have almost
8 | September 2025
two dozen rubber nozzles, called ‘duck bills’. The nozzles will allow periodic release of treated effluent without permitting ingress of sea water into the outfall system. The pontoon is part of a larger
fleet of vessels working on the harbour from Clarks Beach. Piling work has been underway to establish the piled foundations for the large diffuser structure, before it is connected to the bored tunnel outfall. Treated effluent will come from
the Clarks Beach Wastewater Treatment Plant, currently being upgraded. The works are expected to be completed by mid-2026. The outfall is a key component
of a broader infrastructure programme designed to support the projected population growth in Auckland’s south-west, which is expected to reach approximately 30,000 people by 2050. Watercare programme delivery
manager Dave Kennerley said the outfall has been designed and sized to support future population growth. It will store and discharge treated wastewater approximately 100m into the Waiuku Channel – a highly dynamic part of the harbour where it will quickly disperse. Discharges for treated effluent
dispersion will happen on outgoing tides.
pedestrians and cyclists is to run beneath the estuary between the cities of Santos and Guarujá, travel between which is currently served by ferries and small passenger boats. The tunnel will is to have three lanes in
each direction and the concession contract is to cover construction, operation, and maintenance. São Paulo state government took the
project on a procurement roadshow to Europe and changed its plans following the discussions on the infrastructure market’s appetite for the concession deal. Adjustments changed the contractual
base date, revised some major cost items, and re-evaluated the average transportation distance, and traffic projections were updated. There were also more safeguards for the concessionaire, on predictability and contractual protection. The project is a partnership between
the state government, its transport agency (ARTESP), the Ministry of Ports and Airports, the National Waterway Transport Agency (ANTAQ), and the Santos Port Authority. Bid deadline is early September.
TBMs relaunched on Melbourne’s North East Link AUSTRALIA - The two 15.6m-diameter TBMs on the North East Link road tunnel project, in Melbourne, were recently relaunched following servicing and pull throughs in a 30m-deep box at Lower Plenty Road, where they reached earlier this year. TBMs ‘Gillian’ and ‘Zelda’ are driving
the remaining stretch of the 6.5km-long tunnels to Bulleen. The Herrenknecht TBMs are operated
by Spark consortium, comprising Webuild, GS Engineering and Construction, CPB Contractors, China Construction Oceania, Ventia, Capella Capital, John Laing Investments, DIF, and Pacific Partnerships.
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45