PROJECT | CHINA - DALIANGSHAN NO 1 HIGHWAY TUNNEL
Above: An 8m o.d. refurbished gripper TBM was selected to excavate the central pilot tunnel
To meet all the above requirements, the TBM-
bored pilot would need to be large enough to accommodate a two-lane roadway and connect laterally to the main tubes via the project’s 36 smaller cross-passages for people and the 16 vehicle cross- passages.
With these decisions made, the contractor engaged to
complete the TBM pilot tunnel, one of four contractors engaged on the full tunnel project, selected an 8m-diameter refurbished gripper machine. The TBM was assembled on a limited laydown apron at the launch portal, its components having made a difficult
Above: The primary lined TBM pilot tunnel and its continuous conveyor mucking system 32 | September 2024
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53