BANK STATION UPGRADE | TECHNICAL
Primary SFR sprayed concrete lining domed headwall (min. 350mm)
platform tunnel 3
Northern Line southbound
5/263
a joined-up monitoring and inspection plan was used to address any outstanding risks, learning lessons from previous LU upgrade projects to address serviceability impacts that monitoring alone struggles to capture. From an initial list of 287 civil assets at Bank, only 13
indirectly affected locations required strengthening to withstand the changes in loading and deformation to them, despite the substantial tunnelling planned around the operational railway. With greater understanding of the anticipated movements, it was possible to avoid expensive and intrusive mitigation measures that would impact the travelling public, such as propping, jacking of escalators and speed restrictions.
TUNNEL CONNECTIONS At the concept design stage all proposed tunnel connections to the existing infrastructure were designed using traditional hand mined tunnelling methodologies (also referred to as squareworks). There were four SCL cross passages, connecting to the trackside of the 6.5m-diameter existing Northern Line southbound platform tunnel using squareworks openings. This included two 12-ring (cross passages 1 and 2), one 10-ring (cross passage 3) and one 7-ring wide (cross passage 4) openings. The width of each cast iron ring
is 457mm. A further three adits located between the platforms were designed to be constructed using hand- mining. The squareworks designer at concept was concerned
about failure of the existing cast iron tunnel due to ground movement induced by the new works and propagation of tensile cracks within the tunnel segments in and around the bolt holes and through the depth of the segment pans. The Northern Line connections were identified as requiring extensive strengthening works prior to the tunnelling, noting that internal propping in the platform was not an option as the platform had to be kept operational during construction and was already highly congested. The mitigation proposed a series of steel segment
pans that would sit within the existing cast iron segments just around the openings, to be connected using new bolts through the existing holes. The existing cast iron pans on the Northern Line platforms are infilled with plain concrete, which would have to be removed to install the stiffeners. Clearing the pans in the operational platform tunnel in advance of constructing the cross passages (and adits between the platforms) would have required significant enabling works with notable programme and cost implications.
Above, figure 5: SCL construction sequence at CP1
Below, figure 6: Numerical modelling at connections (Left) Northern Line CP 1 & 2, and (right) DLR CP2
NL NB Platform (5/264, CI)
(SCL, temporary) NL-A1
(hand-mined) NL-CP1 (SCL)
(SCL, temporary) NL-A1C
NL-BC2
Cross passage 5/203 (brick)
NL SB Platform (5/263, CI)
NL-AT2 (SCL, temporary) NL-CP2 (SCL)
DLR-CP2AS (SCL)
DLR-CP2 West (SCL)
(6/270, SGI)
DLR arrival platform
(6/270, PCC)
DLR arrival platform
Escalator 3 upper machine chamber (SCL)
DLR-CC (SCL)
DLR-CP2 East (SCL)
DLR departure platform (6/269, PCC)
DLR cross passage (6/207)
DLR concourse (6/201)
DLR cross passage (6/206)
May 2024 | 27
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41