Left, figure 5:
Pressure relief at the TSC during the initial TSC construction phase PHOTO CREDIT: JACOBS
When RFI responses are required, I am responsible for
prioritising the multiple topics whilst also considering any PW changes, and either developing or reviewing the proposed responses prior to formal response to the RFI.
Where suitable, I have encouraged the collaborative
review of RFIs between the TSC teams. As the construction of the TSC TW is still ongoing,
lessons learnt sessions will be held periodically and, where agreeable, changes implemented for the remaining locations.
TSC PERMANENT WORKS The PW of the MW must be capable of operating for a planned working life of 85 years with limited future access due to operation of the power station. They are formed from cast in-situ RC (high strength and low water-cement ratio) structures, which considered a significant number of design cases to account for construction, operation, and maintenance scenarios that may be encountered. Following the completion of the majority of the HPC onshore tunnels and shafts, I shared the lessons that
May 2024 | 15
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41