| NEWS
First Fehmarnbelt tunnel elements soon to immerse DENMARK - Immersion of the first massive precast concrete element for the almost 18km-long Fehmarn project is expected around Q2 this year. The immersion pontoon vessel - ‘Ivy’ -
to lower the elements is undergoing final testing while preparation of the trench continues along the seabed between Denmark and Germany. Approval of the pontoon is almost two
years behind the schedule. Last September the project developer, Femern A/S, said the delay had put project back 18 months. “Our focus is on resolving the current
challenges and finding solutions that will drive the project forward,” said Mikkel Hemmingsen, CEO of Sund & Bælt Holding, which owns Femern A/S. By early this year there had been 15 tunnel
concrete elements cast in the purpose-built factory on Lolland, corresponding to the first 2.7km of the immersed tube tunnel. Delays have pushed back opening of the
road and rail link from 2029 and impacted total construction costs.
Alkimos segment production completed AUSTRALIA - The Alkimos Seawater Alliance recently completed precast segment production for tunnels in the Alkimos Seawater Desalination project in Perth. More than 31,000 segments were produced
for the 2.5km-long intake and 4km-long outfall tunnels. The casting team achieved up to 330 segments in a day. Marine tunnelling started in 2025. Alkimos SeaWater Alliance, led by Acciona
with Water Corporation and Jacobs Group Australia, is responsible for the design, build and operation of the water supply project.
WTC2026 - Muir Wood keynote speaker CANADA - The World Tunnel Congress 2026 organisers have announced that this year’s prestigious Muir Wood lecture will be given by Remo Grandori. Grandori has worked in TBM tunnelling
as tunnel contractor and TBM manufacturer with Seli. He has acted as consultant for TBM design and operation for clients and general contractors, and co-operated with manufacturers in developing new technologies and TBM types. Since 2020 Grandori has been director
of Webuild’s plant and equipment and TBM department. WTC2026 is in Montreal from 15-21 May.
Above: The rebuilt 5.6m-diameter Main Beam TBM, originally manufactured by Robbins in 1991, will bore through a mix of granitic rock beneath Ellicott City. PHOTO CREDIT: Robbins
UK - A Robbins TBM originally manufactured in 1991 has been rebuilt for a flood mitigation project in the state of Maryland. For the project the 5.6m-diameter Main Bean TBM is to bore through a mix of granitic rock beneath Ellicott City to construct the 1.5km-long Ellicott City North Tunnel. The tunnel is central to Howard
County’s Ellicott City Safe and Sound plan, a critical flood mitigation project in Howard County. It is designed to divert
stormwater run-off away from the historic downtown – an area hit by multiple catastrophic floods in recent years. The tunnel is to provide a
diversion flow rate of up to 98,000 litres of water per second during major storm events. The TBM was refurbished at
Robbins’ manufacturing facility in Solon, Ohio, achieved the substantial completion of the factory acceptance test (FAT) late last year. The build was undertaken in
partnership with contractor Kiewit. Robbins said the machine has a distinguished global track
record on tunnel projects. It has excavated tunnels totalling more than 18km and is now entering its next chapter as part of Maryland’s largest stormwater infrastructure project to date. “Robbins and Kiewit share a
long-standing partnership focused on quality TBM rebuilds and performance,” said Robbins vice- president Doug Harding. “We are marking not only the acceptance of the machine, but also a continued commitment to delivering durable tunnelling solutions that meet the evolving demands of major infrastructure projects.” Kiewit area manager Christof
Metzger said Robbins and Kiewit had worked together over the past year to achieve “this milestone of substantial completion of the FAT”. He added: “Synergy efforts
were required and well delivered to get the TBM to increased technical and safety standards.” Excavation is expected to start
in the coming months following launch shaft construction and TBM assembly on site. The TBM’s operational performance is be supported by Robbins’ field service team.
March 2026 | 9
Veteran Robbins TBM rebuilt for flood mitigation project
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45