MADRID METRO | LININGS & FORMWORK
Overcoming various logistical hurdles, above and below ground, had to be achieved to enable timely execution of final concrete lining works in part of the tunnels of Madrid’s new Line 3 extension project. A tight schedule also had to be met and, of course, high technical standards satisfied by the chosen solution, which was elected to be the use of a modular, flexible formwork traveller system. The construction site had limited space. Consequently,
there were the logistical challenges to negotiate on the surface before the formwork traveller could be lowered underground to help the final lining of a 1.4km-long portion of the mined metro tunnel. The solutions found allowed the formwork system to be transported into and moved around the restricted site, and stored. Following above-ground pre-assembly, the 7.5m-long
formwork traveller was then lowered through a narrow shaft, and then moved on steel wheels into position for the lining works. The existing line (Linea 3) runs north-south through
the heart of the Spanish capital, and extends from Moncloa, at its northern end, to Villaverde Alto, at the southern. At the north end, Line 3 interchanges with Line 6
(at Moncloa), and the western terminus of Line 4 (at Arguelles). The line has numerous other interchanges en route south, again crossing Line 6 (at Legazpi). The southern extension of Line 3 will take the metro
line from Villaverde Alto station to El Cesar, which is an intermediate station on the self-contained loop that is Line 12, in the south west corner of the capital. There is an existing, single interchange on the loop,
at Puerta del Sur station in the north portion which ties into Line 10 and thereby the rest of the metro network. The Line 3 extension will be the Line 12 loop’s second tie-in to the city’s wider metro system.
In late 2021 a consortium of Ossa, Azvi, and Cotodisa
was awarded the construction contract for the 2.7km- long extension to Line 3. Main tunnel construction was underway in 2023, along the weaving tunnel alignment. To deal with space restrictions above and below ground, the logistical solutions developed also needed to deliver underground construction efficiency for the final lining works. The chosen system was a formwork traveller
supplied by Doka and used on just over half of the mined tunnel. The traveller included a modular, heavy duty SL-1 supporting system, including steel panels and additional transverse struts which meant wall anchoring was not required for the formwork. The section height and width were 6.1m and 7.8m, respectively Operating to a daily cycle time, after concreting the
struts were removed by forklift, opening up the arched passageway below the formwork to construction traffic. Having come down into the tunnel pre-assembled, the entire system could move forward - on the steel wheels, rolling directly on the concrete floor - as part of the rapid cyclic operations. This meant no rail fixing to the floor was needed for the system move forward. Additionally, a built-in turntable permitted fast adjustments in curved sections of tunnel. With logistics a principal constraint, Doka Spain’s
project manager, Raul Eickelberg, said in a statement. “The modular design of our SL-1 system was particularly advantageous, allowing us to manage the space efficiently.” Madrid Metro’s Line 3 Extension site manager, Gonzalo
Soubrier, said that the system “provided the robustness and flexibility we needed.” He added that the experience brought by the formwork team was “invaluable in overcoming the project’s challenges.” The metro extension is due to be completed later this
year.
Xxxx
Above left: Formwork traveller in position for final lining works Above right: Section of final lining completed, formwork traveller moved on March 2025 | 11
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53